Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Aug 2022 MBBR 4 second lift side wall form work in progress...,Sludge thicker side wall & launder form work in progress...,C-sump & T-sump side wall form work in progress..,Air blower room part column form work in progress Kollam Project HD
04 Aug 2022 Air blower room column reinforcement work in progress..,C-sump& T-sump side wall form work in progress..,Sludge Thickner side wall & Launder form work in progress Kollam Project HD
03 Aug 2022 Air blower room column reinforcement work in progress...,C-sump side wall form work in progress..,Sludge thickner side wall & launder form work in progress..,MBBR 4 side wall second lift form work in progress...(The work had to stopped temporarily due to heavy rain) Kollam Project HD
02 Aug 2022 Due to heavy rain, there was difficulty in carrying out the works Kollam Project HD
01 Aug 2022 Air blower room shoe setting out work & shoe rcc work in progress..,Sludge thickner side wall &launder form work in progress Kollam Project HD
31 Jul 2022 Sludge holding tank side wall form work in progress...,Sludge thickner final lift side wall & launder form work in progress....T-sump second lift reinforcement work in progress..,clarifier manhole chamber side wall second lift reinforcement work in progress Kollam Project HD
30 Jul 2022 Air blower room plinth beam deshuttering and column setting out work in progress... Sludge holding tank sidewall form work in progress...Sludge thickener final lift sidewall and launder form work in progress..Air blower room rcc work completed..centrate sump raft rcc completed.. Clarifier man hole chamber sidewall rcc completed.. Kollam Project HD
29 Jul 2022 Sludge Holding tank side wall form work in progress..,Sludge Thickner side wall second lift reinforcement work in progress..,Sludge shed plinth bottom earth filling work in progress..pre-treatment unit raft beam form work in progress Kollam Project HD
28 Jul 2022 Sludge holding tank side wall form work in progress..,Air blower room column reinforcement work in progress.., Pre-treatment unit raft beam form work in progress Kollam Project HD
27 Jul 2022 1.Pre-treatment unit - Raft beam side form work in progress 2.Air blower room - column reinforcement work in progress 3.Sludge Thickner - Side wall second lift reinforcement work in progress 4.Sludge Holding tank - Side wall form work in progress 5.MBBR 2 - Side wall second lift reinforcement work in progress 6.Filtrate cum Thickness sludge pump house - Earth excavation work in progress Kollam Project HD