| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Aug 2022 | 7 no.s of submersible pumpsets third party testing completed and ready for dispatch.. work for RCC scheduled today for 40.7 m3 for the following components 1. Sludge holding tank side wall 2. sludge thickner and centrate sump wall 3. valve chamber 4. MBBR 1&2 - baffle wall 5. Equlization tank - baffle wall.... | Kollam Project HD | |
| 16 Aug 2022 | Septage Pumphouse plinth beam form work and reinforcement work in progress..Sludge shed part footing form work in progress...Manhole chamber form work in progress.. | Kollam Project HD | |
| 15 Aug 2022 | Equalization tank walkway form work in progress...,Air blower room part column form work in progress | Kollam Project HD | |
| 13 Aug 2022 | MBBR 4 side wall second lift form work in progress..Equalization tank walk way form work in progress | Kollam Project HD | |
| 12 Aug 2022 | Sludge thickner side wall & launder form work in progress...,Manhole chamber second lift form work in progress..,Equalization tank walk way form work in progress..,sludge shed part footing excavation work in progress | Kollam Project HD | |
| 11 Aug 2022 | MBBR 4 side wall second lift form work in progress...,C&T - sump side wall form work in progress...,Clarifier manhole chamber side wall second lift form work in progress...MBBR 2 Baffle wall form work in progress | Kollam Project HD | |
| 10 Aug 2022 | MBBR 2 Baffle wall form work in progress...,C-sump & T-sump side wall form work in progress..,Clarifier chamber side wall second lift form work in progress..,MBBR 4 side wall second lift form work in progress..Equalization tank walk way form work in progress | Kollam Project HD | |
| 09 Aug 2022 | MBBR 4 side wall second lift form work in progress..,T-sump & C-sump side wall form work in progress. | Kollam Project HD | |
| 08 Aug 2022 | MBBR 2 chamber form work in progress...,C-sump & T-sump side wall form work in progress..,Clarifier chamber side wall second lift form work in progress. | Kollam Project HD | |
| 06 Aug 2022 | Air blower room column reinforcement work in progress..,Sludge Thickner side wall & launder form work in progress..,T-sump & C-sump side wall form work in progress..,MBBR 4 side wall second lift form work in progress..,Clarifier manhole chamber side wall second lift form work in progress | Kollam Project HD |