Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Aug 2022 Due to heavy rains the progress of the work has been affected...but the progress of the work that can be done is going ahead...,MBBR 4 side wall second lift form work in progress..,C&T-Sump side wall second lift form work in progress Kollam Project HD
27 Aug 2022 Due to heavy rain, the works had to be temporarily stopped. However, the work that can be done is going...,C&T-Sump side wall second lift form work in progress. Kollam Project Dn AE4
26 Aug 2022 Pre-treatment unit raft beam rcc work in progress...,Centrifuge building part footing rcc work in progress...,Septage pump house plinth beam rcc work in progress..,C&T-Sump second lift form work in progress. Kollam Project HD
25 Aug 2022 Sludge Holding tank side wall second lift form work in progress...,Air Blower room second lift form work in progress...,MBBR 1 chamber reinforcement work in progress. Kollam Project HD
23 Aug 2022 MBBR 1 Chamber rcc work in progress..,MBBR 2 baffle wall rcc work in progress..,Equalization tank baffle wall second lift rcc work in progress...C&T sump side wall second lift reinforcement work in progress Kollam Project HD
22 Aug 2022 Due to heavy rain, the works had to be temporarily stopped. However, the work that can be done is going.......,C-sump & T-sump side wall second lift reinforcement work in progress Kollam Project HD
21 Aug 2022 Sludge holding tank second lift side wall reinforcement work in progress..,Air blower room part column second lift reinforcement & form work in progress...,C&T sump second lift reinforcement work in progress Kollam Project HD
20 Aug 2022 Sledge shed all footings rcc work completed...,Centrifuge building footings reinforcement & Form work in progress...,Air blower room part column second lift reinforcement work & form work in progress..... Component wise hydro test work in progress Kollam Project HD
19 Aug 2022 Air blower room column 2nd lift reinforcement work in progress.., T&C sump 2nd lift column reinforcement work...,sludge holding tank & manhole chamber deshuttering work in progress Kollam Project HD
18 Aug 2022 RCC work completed on 17/08/2022 & 18/08/22 early morning 1. Rcc sidewall of sludge holding tank upto 2.4 m 2. Thickened sludge sump - sidewall - upto 3.40 m sidewall completed 3. Centrate sump - sidewall - 2.40 m completed 4. Valve chamber - upto 2 nd side wall completed 5. Sludge shed footing part - completed 6. Air blower room column -part RCC completed Kollam Project HD