| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Aug 2022 | Due to heavy rains the progress of the work has been affected...but the progress of the work that can be done is going ahead...,MBBR 4 side wall second lift form work in progress..,C&T-Sump side wall second lift form work in progress | Kollam Project HD | |
| 27 Aug 2022 | Due to heavy rain, the works had to be temporarily stopped. However, the work that can be done is going...,C&T-Sump side wall second lift form work in progress. | Kollam Project Dn AE4 | |
| 26 Aug 2022 | Pre-treatment unit raft beam rcc work in progress...,Centrifuge building part footing rcc work in progress...,Septage pump house plinth beam rcc work in progress..,C&T-Sump second lift form work in progress. | Kollam Project HD | |
| 25 Aug 2022 | Sludge Holding tank side wall second lift form work in progress...,Air Blower room second lift form work in progress...,MBBR 1 chamber reinforcement work in progress. | Kollam Project HD | |
| 23 Aug 2022 | MBBR 1 Chamber rcc work in progress..,MBBR 2 baffle wall rcc work in progress..,Equalization tank baffle wall second lift rcc work in progress...C&T sump side wall second lift reinforcement work in progress | Kollam Project HD | |
| 22 Aug 2022 | Due to heavy rain, the works had to be temporarily stopped. However, the work that can be done is going.......,C-sump & T-sump side wall second lift reinforcement work in progress | Kollam Project HD | |
| 21 Aug 2022 | Sludge holding tank second lift side wall reinforcement work in progress..,Air blower room part column second lift reinforcement & form work in progress...,C&T sump second lift reinforcement work in progress | Kollam Project HD | |
| 20 Aug 2022 | Sledge shed all footings rcc work completed...,Centrifuge building footings reinforcement & Form work in progress...,Air blower room part column second lift reinforcement work & form work in progress..... Component wise hydro test work in progress | Kollam Project HD | |
| 19 Aug 2022 | Air blower room column 2nd lift reinforcement work in progress.., T&C sump 2nd lift column reinforcement work...,sludge holding tank & manhole chamber deshuttering work in progress | Kollam Project HD | |
| 18 Aug 2022 | RCC work completed on 17/08/2022 & 18/08/22 early morning 1. Rcc sidewall of sludge holding tank upto 2.4 m 2. Thickened sludge sump - sidewall - upto 3.40 m sidewall completed 3. Centrate sump - sidewall - 2.40 m completed 4. Valve chamber - upto 2 nd side wall completed 5. Sludge shed footing part - completed 6. Air blower room column -part RCC completed | Kollam Project HD |