| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Sep 2022 | T&C - sump final lift...,MBBR 4 second lift side wall..,Sludge shed part column rcc work completed...,Chlorine contact tank wall side , Pre-treatment unit plinth bottom earth filling work in progress..,Air blower room part second lift column reinforcement work in progress..,Equalization tank walk way form work in progress..Air blower room part roof slab & beam form work in progress | Kollam Project HD | |
| 12 Sep 2022 | MBBR 4 second lift side wall..,Sludge holding tank side wall second lift...,Air blower room part column ..,Centrifuge building part footing..,Sledge shed part short column rcc work in progress. | Kollam Project HD | |
| 12 Sep 2022 | MBBR 4 second lift side wall..,Sludge holding tank side wall second lift...,Air blower room part column ..,Centrifuge building part footing..,Sledge shed part short column rcc work in progress. | Kollam Project HD | |
| 06 Sep 2022 | Pre-treatment unit short column rcc work in progress | Kollam Project HD | |
| 05 Sep 2022 | Equalization tank walk way reinforcement work in progress..,Pre-treatment unit short column form work in progress..,CCT side wall water proofing work in progress | Kollam Project HD | |
| 03 Sep 2022 | MBBR 1 next lift chamber form work in progress...,MBBR 2 baffle wall next lift form work in progress...,Equalization tank walkway beam reinforcement work in progress.Pre-treatment unit short column form work in progress | Kollam Project HD | |
| 02 Sep 2022 | MBBR 2 next lift baffle wall form work in progress..,Equalization tank next lift baffle wall form work in progress...,Sludge shed part short column form work in progress..Septage pump house column reinforcement work & shoe fixing work in progress...,(Due to heavy rains the progress of the work has been affected) | Kollam Project HD | |
| 01 Sep 2022 | Equalization tank baffle wall next lift form work in progress..,C&T-sump side wall next lift form work in progress..,Septage pump house column reinforcement work in progress....,(Due to heavy rains the progress of the work has been affected) | Kollam Project HD | |
| 31 Aug 2022 | Concrete work postponed due to heavy rains | Kollam Project HD | |
| 30 Aug 2022 | MBBR 4 side wall second lift form work in progress..,C&T-Sump side wall second lift form work in progress | Kollam Project HD |