Status Date Overall Project Status Project Officer Contact
22 Sep 2022 Pre-treatment unit plinth beam bottom earth filling & compaction work in progress(for pcc)...,Septage pump house column second lift form work in progress..,Sludge holding tank final lift side wall reinforcement work in progress Kollam Project HD
22 Sep 2022 . Kollam Project HD
21 Sep 2022 Sludge shed plinth beam PCC work completed...Sludge holding tank final lift reinforcement work in progress...,Air blower room roof slab form work in progress..,MBBR 2 next lift baffle wall form work in progress Kollam Project HD
20 Sep 2022 Sludge shed plinth pcc work in progress..,Air blower room roof beam form work in progress..,Equalization tank walk way form work in progress..,Centrifuge building plinth bottom earth filling work in progress Kollam Project HD
19 Sep 2022 Pre-treatment unit plinth bottom earth filling work in progress..,Sludge thickner side wall & launder form work in progress. Kollam Project HD
18 Sep 2022 Work for all major components -rcc work _ MBBR -4 numbers upto 2nd sidewall completed, Clarifiers - upto 2nd sidewall completed, Sludge holding tank - upto 2nd lift completed , sludge thickener - upto 2.40m completed, equilization tank upto 4.80m completed, pretreatment unit upto -plinth level completed Kollam Project HD
17 Sep 2022 work for all major components ongoing & 4 components completed Kollam Project HD
16 Sep 2022 Pre-treatment unit plinth beam bottom earth filling work in progress...Equalization tank baffle wall..,MBBR 1 chamber..,MBBR 2 baffle wall ..,centrifuge building part column,part footing..,Sludge holding tank second lift side wall rcc work completed..,Sludge shed column stirupps making work in progress Kollam Project HD
15 Sep 2022 Equalization tank baffle wall rcc work in progress..,MBBR 1 chamber rcc work in progress..,MBBR 2 baffle wall rcc work in progress..,sludge holding tank side wall second lift rcc work in progress...centrifuge building short column rcc work in progress..,sludge shed plinth bottom earth filling work in progress...Air blower room part second lift column rcc work completed Kollam Project HD
14 Sep 2022 Sludge shed plinth bottom earth filling work in progress...Air blower room roof slab & beam form work in progress...,Septage pump house plinth bottom earth filling work in progress.. Kollam Project HD