| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Oct 2022 | MBBR 1 wlkway form work in progress....clarifier to sledge holding tank pipe trench excavation work in progress | Kollam Project HD | |
| 30 Sep 2022 | Pre-treatment unit plinth beam form work & reinforcement work in progress..,MBBR 1 walk way form work in progress | Kollam Project HD | |
| 29 Sep 2022 | Air blower room roof beam reinforcement work in progress..MBBR 1 walk way form work in progress | Kollam Project HD | |
| 28 Sep 2022 | Air blower room roof slab form work & roof beam reinforcement work in progress..MBBR 1,2,3,4 side wall earth filling work in progress | Kollam Project HD | |
| 27 Sep 2022 | Sludge shed plinth beam form work in progress | Kollam Project HD | |
| 26 Sep 2022 | Sludge thickner side wall & launder form work in progress..,Pre-treatment unit part plinth beam reinforcement work & form work in progress..,Sludge shed plinth beam form work in progress. | Kollam Project HD | |
| 25 Sep 2022 | Sludge thickner side wall & launder form work in progress | Kollam Project HD | |
| 24 Sep 2022 | Pre-treatment unit plinth beam reinforcement work in progress...,Sludge shed plinth beam reinforcement work in progress...,Compound wall block work in progress...,MBBR 3,4 side wall earth filling work in progress | Kollam Project HD | |
| 23 Sep 2022 | Pre-treatment unit part plinth bottom earth leveling & compaction work in progress..,Sludge thickner launder side wall form work in progress..,Septage pump house 2nd lift column rcc work in progress..,Pre-treatment unit part plinth reinforcement work in progress | Kollam Project HD | |
| 24 Sep 2022 | Pre-treatment unit part plinth bottom earth leveling & compaction work in progress..,Sludge thickner launder side wall form work in progress..,Septage pump house 2nd lift column rcc work in progress..,Pre-treatment unit part plinth reinforcement work in progress | Kollam Project HD |