| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Oct 2022 | Pre-treatment unit plinth beam form work in progress..,Controll unit soil investigation work in progress..,Sludge shed column shoe settin out work in progress | Kollam Project HD | |
| 09 Oct 2022 | All components wall side earth filling work in progress..,Control unit soil investigation work in progress | Kollam Project HD | |
| 08 Oct 2022 | Clarifier 1 shaft pipe fixing work in progress..,Sludge shed column shoe setting out work in progress..,pipe bottom anchor block reinforcement work in progress..,components wall side earth filling work in progress | Kollam Project HD | |
| 07 Oct 2022 | Clarifier-MBBR effluent pipe laying work in progress...,Sludge shed plinth beam rcc work in progress..,Control unit soil investigation work in progress. | Kollam Project HD | |
| 06 Oct 2022 | Sludge pipe line earth excavation work in progress...,MBBR 1 walk way form work in progress | Kollam Project HD | |
| 05 Oct 2022 | MBBR 2 to Clarifier 1 pipe line trench excavation work in progress | Kollam Project HD | |
| 04 Oct 2022 | Pooja holiday | Kollam Project HD | |
| 03 Oct 2022 | MBBR 1 walk way form work in progress | Kollam Project HD | |
| 02 Oct 2022 | MBBR 1 walk way form work in progress...components side earth filling work in progress | Kollam Project HD | |
| 03 Oct 2022 | MBBR 1 walk way form work in progress...components side earth filling work in progress | Kollam Project HD |