Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Oct 2022 Air blower room roof slab & beam reinforcement work in progress...,Sludge thickner to t-sump pipe laying work in progress..,Sludge shed column form work in progress Kollam Project HD
20 Oct 2022 Air blower room roof slab form work & reinforcement work in progress..,Sludge shed column form work in progress..,Sludge thicker to T-Sump pipe laying work in progress...,Pre-treatment unit column reinforcement work in progress Kollam Project HD
19 Oct 2022 Sludge shed column reinforcement work & form work in progress..,Air blower room roof slab form work in progress...,Pre-treatment unit column reinforcement work in progress...,Sludge pipe line trench earth excavation work in progress...,Sludge pump house footing earth excavation work in progress Kollam Project HD
18 Oct 2022 Sludge pipe laying work in progress..,Air blower room roof slab form work in progress..,Pre-treatment unit Column reinforcement work in progress...,Sludge shed Column reinforcement work in progress Kollam Project HD
16 Oct 2022 Air blower room roof beam reinforcement work in progress..,Pre-treatment unit column reinforcement work in progress Kollam Project HD
15 Oct 2022 1.The progress of the work last week on 07-10-2022(10.00 M3) of rcc work completed for sludge shed.., 2.On 12-10-2022(10.00 M3) of rcc work completed for Pre-treatment unit 3.MBBR 4 to Clarifier 2..,MBBR 3 to Clarifier 1 Pipe laying work in progress 4.Sludge Holding tank to Clarifier manhole chamber pipe line trench earth excavation work in progress 5.Air blower room roof beam reinforcement work in progress 6.Sludge pump house footing part pcc work completed(4.00 M3) Kollam Project HD
14 Oct 2022 Sludge pipe line trench earth excavation work in progress...,septage pump house footing pcc form work & pcc work in progress Kollam Project HD
13 Oct 2022 Sludge pipe line trench excavation work in progress..,Pre-treatment unit plinth beam rcc work completed..Sludge pump house column footing setting out work in progress Kollam Project HD
12 Oct 2022 Sludge pipe laying work & second chamber earth excavation work in progress..,Pre-treatment unit plinth rcc work in progress Kollam Project HD
11 Oct 2022 Pre-treatment unit plinth beam form work in progress..,Sludge pipe laying work in progress...pipe bottom anchor block rcc work in progress Kollam Project HD