| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Oct 2022 | Pre-treatment unit column reinforcement work in progress..,sludge shed roof beam side board making work in progress..,pre-treatment unit column box making work in progress | Kollam Project HD | |
| 30 Oct 2022 | Air blower Roof slab rcc work in progress | Kollam Project HD | |
| 29 Oct 2022 | Air blower room roof slab reinforcement work in progress..,Pre- treatment unit column stater setting out & rcc work in progress | Kollam Project HD | |
| 28 Oct 2022 | Air blower room roof slab reinforcement work in progress..,Sludge shed column second lift rcc work in progress..,Clarifier control chamber no : 3 earth excavation work in progres | Kollam Project HD | |
| 27 Oct 2022 | Air blower room roof slab reinforcement work in progress..,Sludge shed column second lift form work in progress..,MBBR 1 side wall & walkway form work in progress..,Clarifier control chamber no : 3 earth excavation work in progress | Kollam Project HD | |
| 26 Oct 2022 | Air blower room slab reinforcement work in progress..,Sludge shed column second lift form work in progress..,Clarifier manhole chamber earth excavation work in progress...Sludge thickner launder slab reinforcement work in progress | Kollam Project HD | |
| 25 Oct 2022 | Air blower room roof slab form work & reinforcement work in progress..,Sludge shed column next lift form work in progress | Kollam Project HD | |
| 24 Oct 2022 | Air blower room roof slab form work & reinforcement work in progress | Kollam Project HD | |
| 23 Oct 2022 | Air blower room roof slab form work & reinforcement work in progress..,Sludge shed column deshuttering work in progress | Kollam Project HD | |
| 22 Oct 2022 | Sludge shed part column rcc work completed. | Kollam Project HD |