Status Date Overall Project Status Project Officer Contact
09 Nov 2022 Pre-treatment unit stilling chamber bottom slab rcc work in progress...,Equalization tank baffle wall final lift rcc work in progress..,MBBR 3 baffle wall second lift rcc work in progress..,Sledge holding tank side wall final lift form work in progress..,Sledge thickner side wall final lift form work in progress. Kollam Project HD
08 Nov 2022 Pre-treatment unit part column form work in progress...,Sledge pump house footing reinforcement & form work in progress..,Sledge shed roof slab form work in progress..,Equalization tank baffle wall final lift form work in progress. Kollam Project HD
07 Nov 2022 Equalization tank baffle wall final lift form work in progress..,Sludge shed roof slab form work in progress..,Stilling chamber bottom slab reinforcement work in progress...,Sledge pump house footing reinforcement work in progress. Kollam Project HD
06 Nov 2022 Sludge shed roof slab form work in progress..,Sledge pump house footing reinforcement work in progress. Kollam Project HD
05 Nov 2022 Equalization baffle wall final lift form work in progress..,Sludge shed roof slab beam bottom form work in progress..,MBBR 1 final lift side wall & walk way form work in progress.Stilling chamber slab reinforcement work & form work in progress Kollam Project HD
04 Nov 2022 Pre-treatment unit part column form work in progress...,Equalization baffle wall final lift form work in progress..,Sludge shed roof slab bottom scaffolding work in progress..,MBBR 1 final lift side wall & walk way form work in progress. Kollam Project HD
04 Nov 2022 Pre-treatment unit column rcc work in progress...,Equalization baffle wall final lift form work in progress..,Sludge shed roof slab bottom scaffolding work in progress..,MBBR 1 final lift side wall & walk way form work in progress. Kollam Project HD
03 Nov 2022 Sludge thickner launder slab rcc work in progress...,Pre-treatment unit column rcc work in progress...,Equalization baffle wall final lift form work in progress Kollam Project HD
02 Nov 2022 70 % Completed..,Sludge shed roof slab scaffolding work in progress..,Pre-treatment unit column form work in progress..,Sludge thickner launder reinforcement work in progress..,Sludge holding tank final lift reinforcement work in progress Kollam Project HD
01 Nov 2022 Sludge shed roof slab scaffolding work in progress..,Pre-treatment unit column form work in progress..,Sludge thickner launder reinforcement work in progress Kollam Project HD