| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Apr 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4968nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 15 Apr 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4950nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 08 Apr 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4950nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 05 Apr 2025 | Package-1- Old Muncipal area in Kollam corporation - 67 % completed, 774 nos FHTCs are given,Total Pipe laid till date-9507.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1346 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4950nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 29 Mar 2025 | Package-1- Old Muncipal area in Kollam corporation - 67 % completed, 774 nos FHTCs are given,Total Pipe laid till date-9507.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1346 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4873 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 26 Mar 2025 | Package-1- Old Muncipal area in Kollam corporation - 67 % completed, 774 nos FHTCs are given,Total Pipe laid till date-9507.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1346 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4845 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 26 Mar 2025 | Package-1- Old Muncipal area in Kollam corporation - 67 % completed, 774 nos FHTCs are given,Total Pipe laid till date-9507.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1346 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4845 nos FHTCs are completed.(previously this number is wrongly entered as 4863 instead of 4836,which is rectified now) . Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 22 Mar 2025 | Package-1- Old Muncipal area in Kollam corporation - 67 % completed, 774 nos FHTCs are given,Total Pipe laid till date-9507.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1331 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4836 nos FHTCs are completed.(previously this number is wrongly entered as 4863 instead of 4836,which is rectified now) . Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 18 Mar 2025 | Package-1- Old Muncipal area in Kollam corporation - 60 % completed, 711 nos FHTCs are given,Total Pipe laid till date-8621 m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1292 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4863 nos FHTCs are completed . Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 14 Mar 2025 | Package-1- Old Muncipal area in Kollam corporation - 60 % completed, 711 nos FHTCs are given,Total Pipe laid till date-8621 m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 76 % completed ,1292 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4818 nos FHTCs are completed . Total Pipe laid till date-11664 m. | Kollam WS Sn 2 - AE |