| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Jun 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 03 Jun 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 30 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 27 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1503 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 22 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1469 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 17 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1459 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 13 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1395 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 09 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5015nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 02 May 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5015nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 25 Apr 2025 | Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4994nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE |