Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
03 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
30 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
27 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1503 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
22 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1469 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
17 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1459 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
13 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1395 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
09 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5015nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
02 May 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5015nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
25 Apr 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 77 % completed ,1378 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 4994nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE