Status Date Overall Project Status Project Officer Contact
07 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 77 % completed, 956 nos FHTCs are given,Total Pipe laid till date-10805.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
04 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 77 % completed, 956 nos FHTCs are given,Total Pipe laid till date-10805.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
04 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 77 % completed, 956 nos FHTCs are given,Total Pipe laid till date-10805.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
01 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 72 % completed, 920 nos FHTCs are given,Total Pipe laid till date-10050.8m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
25 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 71 % completed, 850 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5135nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
20 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 71 % completed, 850 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5135nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
17 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 850 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1594 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5135nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
16 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1580 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
11 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1527 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
09 Jun 2025 Package-1- Old Muncipal area in Kollam corporation - 70 % completed, 785 nos FHTCs are given,Total Pipe laid till date-9816.50m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 78 % completed ,1517 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5035nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE