| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jul 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Memala tank connection completed. Tank at Kambipalam and Parathod on progress. Demand Notice received for line extension and amount remmitted to KSEB, Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 08 Jul 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Memala tank connection completed. Tank at Kambipalam and Parathod on progress. Demand Notice received for line extension and amount remmitted to KSEB, Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 05 Jul 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Memala tank connection completed. Tank at Kambipalam and Parathod on progress. Demand Notice received for line extension and amount remmitted to KSEB, Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 27 Jun 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Memala tank connection completed. Tank at Kambipalam and Parathod on progress. Demand Notice received for line extension and amount remmitted to KSEB, Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 13 Jun 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Memala tank connection completed. Tank at Kambipalam and Parathod on progress. Demand Notice received from KSEB for line extension , Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 07 Jun 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Waiting for KSEB connection , Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 03 Jun 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Waiting for KSEB connection , Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 29 May 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Waiting for KSEB connection , Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 25 May 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 - Waiting for KSEB connection , Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)- KSEB Power connection process on going , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 | |
| 21 May 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Charging work started .package 3 - Tank connection work in Progress , Package 4 (part -I) - Waiting for KSEB connection , Package 4 (part II)-KSEB Power connection process on going. , Package 5 -Pumpset and transformer commisioning on progress, Package 5 II - Erection work completed and waiting for KSEB connection | Koothuparamba Proj AE 2 |