| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jan 2021 | 1) Package 1 (WTP and allied works) - Work Held up due to public protest against earth work at WTP site..2) Package II (Distribution) - Work agreement executed. Pipes Supply order placed by the contractor. 3) Package III (Power Line Extension and Transformer through KSEB) - Payment towards the HT A ABC powerline extension to WTP site remitted to KSEB . work initiated by KSEB | Malappuram Project Dn | |
| 14 Dec 2020 | 1) Package 1 (WTP and allied works) - Work Held up due to public protest against earth work at WTP site..2) Package II (Distribution) - Work awarded on 06.11.2020. 3) Package III (Power Line Extension and Transformer through KSEB) - Payment towards the HT A ABC powerline extension to WTP site remitted to KSEB on 12.11.2020. Awaiting further action from KSEB for the work. | Malappuram Project Dn | |
| 17 Nov 2020 | 1) Package 1 (WTP and allied works) - 7% Hydraulic & Structural Design has been submitted to Government Engineering College for Verification, Supply order for pipes have been placed. 2) Package II (Distribution) - Work awarded on 06.11.2020. 3) Package III (Power Line Extension and Transformer through KSEB) - Payment towards the HT A ABC powerline extension to WTP site remitted to KSEB on 12.11.2020. Awaiting further action from KSEB for the work. | Malappuram Project Dn | |
| 11 Oct 2020 | 1) Package 1 (WTP and allied works) - 6% (hydraulic Design has been submitted to Government Engineering College for Verification, Supply order for pipes have been placed 2) Package II (Distribution) - Request for Approval of Tender has been submitted to Head Office 3) Package III (Power Line Extension and Transformer through KSEB) - Package Confirmation Obtained from KIIFB and WBS approval procedure is progressing through KIIFB-PFMS | Malappuram Project Dn | |
| 16 Aug 2020 | 1) Package 1 (WTP and allied works) - 4% (Design is progressing) 2) Package II (Distribution) - Tendered 3) Package III (Power Line Extension and Transformer through KSEB) - Package Confirmation Obtained from KIIFB | Malappuram Project Dn |