KIIFB – PROJECT TRANCHE-8-WRD025 - 14 WSS to Edavanna Panchayath in Malappuram District

Project KIIFB – PROJECT TRANCHE-8-WRD025 - 14 WSS to Edavanna Panchayath in Malappuram District
Project Code MLPKIIFB0218679
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Project includes the following Components : 1.9.0MLD WTP with Full Automation SCADA and allied works. 2.2 Nos of OHSR's(18.20 LL &11.90 LL) 3. 400mm DI -RW pumping main--1950m 4Transformers,Power line extenstion and Shifting of Electric poles, 5.RW and CW Pumpsets(216 HP VT &20HP CF) 6. Wash waterPipe line-300mm dia DI K7-1050m 7 Distribution System-178Km (Pipes dia varies from 90mmPVC pipe to 350mm DI K9 pipes) Other Details: Expected annual revenue when project is completed: 80Lakhs/Annum Ratio of material and labour,: 60:40 Total cost of the project, : 472100000 Source of funding, : KIIFB Date of AS, : 06.02.2018 Date of signing the agreement, ;17.03.2020 Scheduled date of completion,: 05.05.2022 Time overrun in Days/ weeks : Officer now responsible for execution. : Executive Engineer : ANSAR. Assistant Executive Engineer: BINDU. Assistant Engineer : ABDUL HAMEED
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 472120000
AS Number WRD-025-14-PA-01
TS Amount (Rs) 311300000
TS Number 3450/2020-21
Total Bill Submitted (Rs) 325754458
Total Bill Paid (Rs) 325754458
Population Benefitted 75620
Capacity in MLD 9.00
Actual Project Completion Date 16 May 2022
Coverage Edavanna Gramapanchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 BUDGET 2017-18 KIIFB: WRD-025-14-WSS TO EDAVANNA PANCHAYATH OF MALAPPURAM DISTRICT PACKAGE-2 DISTRIBUTION SYSTEM. Project Division Malappuram
2 KIIFB-PROJECT TRANCHE-8-WRD- 025-14-COMPREHENSIVE DRINKING WATER SUPPLY SCHEME TO EDAVANNA PANCHAYATH IN MALAPPURAM DISTRICT - PACKAGE-I Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Nov 2023 Package -I and Package II of the scheme 90 % completed and the trial run has successfully completed on 10-5-2023.charging of distribution line progressing Malappuram Project Dn
06 Oct 2023 Package -I and Package II of the scheme 90 % completed and the trial run has successfully completed on 10-5-2023. Malappuram Project Dn
06 Sep 2023 Package -I and Package II of the scheme 90 % completed and the trial run has successfully completed on 10-5-2023. Malappuram Project Dn
13 Aug 2023 Package -I and Package II of the scheme 90 % completed and the trial run has successfully completed on 10-5-2023. Malappuram Project Dn
13 Jul 2023 Package -I and Package II of the scheme 90 % completed and the trial run has successfully completed on 10-5-2023. Malappuram Project Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/03/2020
Scheduled date of Completion of the Project 05 May 2022
Expected date of Completion 30/04/2023

Processing Dates

AS Date 06 Feb 2018
TS Date 12 Dec 2019

Other details

Project Officers View