Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Oct 2021 | GI,MS pipe work progressing | Malappuram Project Dn | |
06 Oct 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. | Malappuram Project Dn | |
04 Oct 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. | Malappuram Project Dn | |
30 Sep 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. | Malappuram Project Dn | |
27 Sep 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. | Malappuram Project Dn | |
22 Sep 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 80 km already laid. | Malappuram Project Dn | |
21 Sep 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 80 km already laid. | Malappuram Project Dn | |
10 Sep 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 80 km already laid. | Malappuram Project Dn | |
08 Sep 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 80 km already laid. | Malappuram Project Dn | |
31 Aug 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 70 km already laid. | Malappuram Project Dn |