| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 14 Jul 2021 | Package I PCC of filter unit started - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 14 Jul 2021 | Package I PCC of filter unit started - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 13 Jul 2021 | There is no work today due to heavy rain. | Malappuram Project Dn | |
| 12 Jul 2021 | Package I PCC of filter unit started - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. Todays heavy rain work interupted | Malappuram Project Dn | |
| 11 Jul 2021 | Package I PCC of filter unit started - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid | Malappuram Project Dn | |
| 11 Jul 2021 | Package I PCC of filter unit started - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid | Malappuram Project Dn | |
| 09 Jul 2021 | In Package I PCC of filter unit started - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid | Malappuram Project Dn | |
| 08 Jul 2021 | Earth work for sump, clarifloculator completed, structural work is going on in Package I -pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid | Malappuram Project Dn | |
| 05 Jul 2021 | Earth work for sump, clarifloculator completed, collection of materials for structural work is going on in Package I -pipe line work in progressing in Package II | Malappuram Project Dn |