| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Jul 2021 | Earth work for sump, clarifloculator completed, collection of materials for structural work is going on in Package I -pipe line work in progressing in Package II | Malappuram Project Dn | |
| 30 Jun 2021 | Earth work for sump, clarifloculator completed, collection of materials for structural work is going on in Package I -pipe line work in progressing in Package II | Malappuram Project Dn | |
| 28 Jun 2021 | Earth work for sump, clarifloculator completed, collection of materials for structural work is going on. | Malappuram Project Dn | |
| 22 Jun 2021 | Earth work for sump, clarifloculator completed, strucutral work started, waiting for MTC.package I19% completed, package II 35% complted and is in progressing. DI pipe for pumping main P-I supplied | Malappuram Project Dn | |
| 21 Jun 2021 | Earth work for sump, clarifloculator completed, strucutral work started, waiting for MTC.package I19% completed, package II 35% complted and is in progressing. DI pipe for pumping main P-I supplied | Malappuram Project Dn | |
| 17 Jun 2021 | Earth work for sump, clarifloculator completed, strucutral work started, waiting for MTC.package I19% completed, package II 35% complted and is in progressing. | Malappuram Project Dn | |
| 16 Jun 2021 | Package-1- 18% completed. Package-2-35% completed. Today work disturbed due to heavy rain | Malappuram Project Dn | |
| 15 Jun 2021 | Package-1- 18% completed. Package-2-35% completed.Laying work in progress | Malappuram Project Dn | |
| 01 Jun 2021 | Work restated after tripple lock down - earth work for column progressing . | Malappuram Project Dn | |
| 31 May 2021 | Temporarily stopped due to cowid 19 tripple lock down | Malappuram Project Dn |