Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jan 2022 Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . Malappuram Project Dn
12 Jan 2022 Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . Malappuram Project Dn
21 Dec 2021 Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 135 Km pipe supplied , 105 km of various dia pipes laid, GI, MS work progressing . Malappuram Malappuram Project Dn
15 Nov 2021 Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Package II- 105 Km pipe supplied , 90 km of various dia pipes laid, GI, MS work progressing . Malappuram Malappuram Project Dn
08 Nov 2021 Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Package II- 105 Km pipe supplied , 90 km of various dia pipes laid, GI, MS work progressing . Malappuram Project Dn
25 Oct 2021 Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Project Dn Malappuram Project Dn
22 Oct 2021 Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Project Dn
20 Oct 2021 Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Project Dn
12 Oct 2021 Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Project Dn
11 Oct 2021 Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Malappuram Project Dn