| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jan 2022 | Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . Malappuram Project | Malappuram Project Dn | |
| 13 Jan 2022 | Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . | Malappuram Project Dn | |
| 12 Jan 2022 | Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . | Malappuram Project Dn | |
| 21 Dec 2021 | Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 135 Km pipe supplied , 105 km of various dia pipes laid, GI, MS work progressing . Malappuram | Malappuram Project Dn | |
| 15 Nov 2021 | Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Package II- 105 Km pipe supplied , 90 km of various dia pipes laid, GI, MS work progressing . Malappuram | Malappuram Project Dn | |
| 08 Nov 2021 | Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Package II- 105 Km pipe supplied , 90 km of various dia pipes laid, GI, MS work progressing . | Malappuram Project Dn | |
| 25 Oct 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Project Dn | Malappuram Project Dn | |
| 22 Oct 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. | Malappuram Project Dn | |
| 20 Oct 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. | Malappuram Project Dn | |
| 12 Oct 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. | Malappuram Project Dn |