Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Jan 2022 |
Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . |
Malappuram Project Dn |
|
12 Jan 2022 |
Package I filter, clarifier unit SUMP etc. work completed. OHSR floor slab completed side wall progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 165 Km pipe supplied , 132 km of various dia pipes laid, GI, MS work progressing . |
Malappuram Project Dn |
|
21 Dec 2021 |
Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Plastering work started - Package II- 135 Km pipe supplied , 105 km of various dia pipes laid, GI, MS work progressing . Malappuram |
Malappuram Project Dn |
|
15 Nov 2021 |
Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed. Package II- 105 Km pipe supplied , 90 km of various dia pipes laid, GI, MS work progressing . Malappuram |
Malappuram Project Dn |
|
08 Nov 2021 |
Package I filter, clarifier unit SUMP etc. Structural work at the finishing stage,Ohsr ,aerator, flashmixer unit etc.work progressing.Power line extension and erection of transformer completed.
Package II- 105 Km pipe supplied , 90 km of various dia pipes laid, GI, MS work progressing . |
Malappuram Project Dn |
|
25 Oct 2021 |
Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram Project Dn |
Malappuram Project Dn |
|
22 Oct 2021 |
Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. |
Malappuram Project Dn |
|
20 Oct 2021 |
Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. |
Malappuram Project Dn |
|
12 Oct 2021 |
Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. |
Malappuram Project Dn |
|
11 Oct 2021 |
Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 85 km already laid. GI, MS work progressing. Malappuram |
Malappuram Project Dn |
|