| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Mar 2021 | direction given to the contractor for starting the work | Malappuram Project Dn | |
| 07 Mar 2021 | replay obtained from geologist on 23/2/2021 direction given to the contractor for starting the work | Malappuram Project Dn | |
| 25 Feb 2021 | replay obtained from geologist on 23/2/2021 direction given to the contractor for starting the work | Malappuram Project Dn | |
| 23 Feb 2021 | replay obtained from geologist on 23/2/2021 direction given to the contractor for starting the work. | Malappuram Project Dn | |
| 22 Feb 2021 | awaiting replay from geolagist(gwd) | Malappuram Project Dn | |
| 10 Feb 2021 | Package-1-Work commenced. Work held up due to local protest against the earth levelling at WTP site. The work will restarted on the recommendation from Geology Dept. Package-II-Distribution System-5978m 300&350mm DI pipes supplied by the contractor. Balance pipes and specials supply order placed by the contractor. Package-III- Work initiated by the KSEB Ltd, Work temporarily stopped due to public protest against the earth work excavation in Package-I work. The work will be restarted after getting decision on package-I work | Malappuram Project Dn | |
| 06 Feb 2021 | Package-1-Work commenced. Work held up due to local protest against the earth levelling at WTP site. Honb'le. MLA and Panchayath authorities conducted the meeting with protesters and decided to conduct Geological tests . Minning and Geological Dept. test scheduled on 04.02.2021. The work will restarted on the recommendation from Geology Dept. Package-II-Distribution System-5978m 300&350mm DI pipes supplied by the contractor. Balance pipes and specials supply order placed by the contractor. Package-III- Work initiated by the KSEB Ltd, Work temporarily stopped due to public protest against the earth work excavation in Package-I work. The work will be restarted after getting decision on package-I work | Malappuram Project Dn | |
| 04 Feb 2021 | Package-1-Work commenced. Work held up due to local protest against the earth levelling at WTP site. Honb'le. MLA and Panchayath authorities conducted the meeting with protesters and decided to conduct Geological tests . Minning and Geological Dept. test scheduled on 04.02.2021. The work will restarted on the recommendation from Geology Dept. Package-II-Distribution System-5978m 300&350mm DI pipes supplied by the contractor. Package-III- Work initiated by the KSEB Ltd, ork temporarily stopped due to public protest against the earth work excavation in Package-I work. The work will be restarted after getting decision on package-I work. | Malappuram Project Dn | |
| 02 Feb 2021 | 1) Package 1 (WTP and allied works) - Work Held up due to public protest against earth levelling work at WTP site..2) Package II (Distribution) - . Pipes Supply order placed by the contractor. 3) Package III (Power Line Extension and Transformer through KSEB) - Payment towards the HT A ABC powerline extension to WTP site remitted to KSEB . work initiated by KSEB | Malappuram Project Dn | |
| 26 Jan 2021 | 1) Package 1 (WTP and allied works) - Work Held up due to public protest against earth work at WTP site..2) Package II (Distribution) - . Pipes Supply order placed by the contractor. 3) Package III (Power Line Extension and Transformer through KSEB) - Payment towards the HT A ABC powerline extension to WTP site remitted to KSEB . work initiated by KSEB | Malappuram Project Dn |