| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Jul 2021 | Package I filter, clarifier unit SUMP etc. work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 28 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 26 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 23 Jul 2021 | Package I filter, clarifier unit work progressing. | Malappuram Project Dn | |
| 23 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 22 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 20 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 20 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 19 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn | |
| 17 Jul 2021 | Package I filter, clarifier unit work progressing - pipe line work in progressing in Package II- 102 km pipe supplied- 46 km already laid. | Malappuram Project Dn |