| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Mar 2024 | Work in progress..-24.80 km out of 36.5 laid.Interconnection and Fhtc work in progress... | Kollam Project HD | |
| 23 Mar 2024 | Work in progress..-24.80 km out of 36.5 laid..Fhtc and Valve fixing and Interconnection progress...Backfilling and Geotagging progress... | Kollam Project HD | |
| 22 Mar 2024 | Work in progress..-24.80 km out of 36.5 laid..Fhtc and Interconnection progress...GI work and Geotagging progress... | Kollam Project HD | |
| 21 Mar 2024 | Work in progress..-24.80 km out of 36.5 laid..Fhtc and Interconnection progress...GI work and Geotagging progress... | Kollam Project HD | |
| 20 Mar 2024 | Work in progress..-24.80 km out of 36.5 laid..Fhtc and Interconnection progress...Geotagging progress... | Kollam Project HD | |
| 19 Mar 2024 | Work in progress..-24.41 km out of 36.5 laid..Excavation and laying work in progress... FHTC and Geotagging progress... | Kollam Project HD | |
| 18 Mar 2024 | Work in progress..-24.41 km out of 36.5 laid..Fhtc and Geotagging progress... | Kollam Project HD | |
| 16 Mar 2024 | Work in progress..-24.41 km out of 36.5 laid..Fhtc work and .Di pipe Anchor block concrete work in progress..Geotagging progress... | Kollam Project HD | |
| 15 Mar 2024 | Work in progress..-24.41 km out of 36.5 laid..Fhtc work and DI work in progress... | Kollam Project HD | |
| 14 Mar 2024 | Work in progress..-24.41 km out of 36.5 laid.. FHTC and Backfilling work in progress...DI work in progress...@ Varkkala road | Kollam Project HD |