Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 May 2023 Work foreclosed by tendering authority. Thiruvananthapuram Project AE3
22 Apr 2023 Vide KWA Board decision on Item No. IX(5) of the 431st Board meeting of KWA held on 01-03-2022, directed SE, PHC, Tvpm to close the work as per agreement conditions and take action to complete the balance works by rearranging. Thiruvananthapuram Project AE3
27 Jan 2023 Vide Proceedings of SE, PHC, TVPM no. No: KWA/PHC/TVM/D5/6528/15 dated 28-12-2022, Time of completion extended from 31-03-2022 upto 30-04-2023 in accordance with the original agreement condition, but contractor has not executed the supplementary agreement till date. Also contractor has filed a writ petition in Hon. High Court, Kerala against non consideration of greivances of the contractor and above extension of time period. Thiruvananthapuram Project AE3
05 Nov 2022 Time of completion of the work extended for 6 months vide KWA board decision and MD, KWA proceedings. Thiruvananthapuram Project AE3
15 May 2022 Road restoration work of Nalanchira Kusavarkal road - Corporation road started. 1118 mm MS Bend welded and pipe attached for fixing 1100mm Sluice valve near NPP Nagar, Peroorkada. Trench backfilling done at Kudappanakunnu-Pathirapally MLA road and NPP Nagar, Peroorkada. Thiruvananthapuram Project AE3
09 May 2022 1100mm Sluice valve chamber pit taken near and chamber construction to be started. 1100mm MS bend welded and pipe to be attached for interconnection to Peroorkada GLSR. Laying of 914mm MS pipe in progress at MLA road, Near Pathirapally. Thiruvananthapuram Project AE3
06 May 2022 Rock breaking near NPP Nagar almost completed. Sluice valve chamber for 1100mm SV excavated. Valve chamber to be constructed and valve to be erected. Road restoration work ongoing in MLA road, Pathirappally. 2 nos of 12m of 914mm MS pipe laid in MLA road, pathirappally. Thiruvananthapuram Project AE3
03 May 2022 Rock breaking near Church/KWA Compound completed for interconnection to Peroorkada GLSR and bends welded. Sluice valve chamber excavation almost completed near NPP Nagar. Road restoration work of 40mm Chipping carpet surface ongoing in Kudappanakunnu-Krishna nagar road. Excavation started for laying 914mm MS pipe in MLA road started. Thiruvananthapuram Project AE3
30 Apr 2022 3 nos. of 6m - 1118mm MS pipe laid near NPP Nagar, Peroorkada after rock breaking and removal. Rock breaking near Church, KWA Compound back side, Peroorkada in progress. Final layer chipping carpet tarring of Kudappanakunnu-Krishna Nagar road scheduled on 02.05.22. Thiruvananthapuram Project AE3
28 Apr 2022 2 nos. of 6m - 1118mm MS pipe laid near NPP Nagar Lane-1, Peroorkada. Rock removal almost completed for laying 3rd 6m pipe at the said location. Afterwards chamber construction for 1100mm Sluice valve can be started. Rock breaking near Church, KWA Compound, Peroorkada in progress. Final layer of road tarring work at Kudappanakunnu-Krishna Nagar road not started. Thiruvananthapuram Project AE3