Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Mar 2022 Hydrostatic pressure test conducted successfully for 600mm DI pipe for 487m reach near Karumbumkonam towards Kariyam road. Road restoration of GSB and WMM layer completed at MC road, from AMSET jn to Kurissady junction, Nalanchira. Culvert reconstruction completed at 1118mm MS pipe laying location at Krishna Nagar, Peroorkada. Rock breaking and removal ongoing at Peroorkada. Thiruvananthapuram Project AE3
16 Mar 2022 Road restoration work at MC road from AMSET junction to Kurissady junction, Nalanchira is progressing. Laying of 600mm DI pipe completed from Karumbumkonam to Kariyam road. Preparations for hydrotest ongoing. Culvert reconstruction work at Krishna Nagar road, Peroorkada ongoing. Rock breaking and removal work near Peroorkada-NPP Nagar lane-1 entrance is progressing. Thiruvananthapuram Project AE3
14 Mar 2022 Welding and allied works in progress at 1118mm MS pipe laying location at Krishna Nagar, Peroorkada. Rock breaking and removal in progress at Peroorkada. Laying of 600mm DI pipe in progress at Karumbumkonam towards Kariyam. Anchor block construction of 600mm DI 22.5 degree bend done. Preparations for hydrostatic pressure test of 600mm DI first stretch of 435m in progress. Thiruvananthapuram Project AE3
11 Mar 2022 Laying of 1118mm MS pipe progressing at Krishna Nagar road, Peroorkada. Laying of 600mm DI pipe ongoing near karumbumkonam. Anchor block construction going on for bends of 600mm DI pipe laid. Air valve chamber and scour valve chamber constructed for 600mm DI pipe laid. MC road restoration works (BMBC surface) started. Thiruvananthapuram Project AE3
08 Mar 2022 Hydrostatic pressure test conducted successfully for 650m of 914mm MS pipe laid from Kurissady junction towards Kusavarkal road. Laying of 1118mm MS pipe progressing at Krishna Nagar road, Peroorkada. Laying of 600mm DI pipe progressing from Karumbumkonam towards Kariyam junction. Road restoration work also progressing in the above stretch. Thiruvananthapuram Project AE3
06 Mar 2022 Laying of 600mm DI pipe progressing from Karumbumkonam junction towards Kariyam junction. Road restoration work of Corporation road at VRK started. Laying of 1118mm MS pipe progressing at Krishna Nagar road, Peroorkada. Road restoration work (up to emulsion spraying over wet mix) of PWD BM & BC road in MC road is planning to start on 08/03/22.. Rock breaking and removal ongoing at Peroorkada. Hydrotest water filled at Kurissady junction-Kusavarkal road, Nalanchira.testing scheduled on 07.03.22 Thiruvananthapuram Proj Dn AEE 2
02 Mar 2022 Laying of 600mm DI pipe progressing from Karumbumkonam junction towards Kariyam junction. Road restoration work of Corporation road at VRK road yet to start. Laying of 1118mm MS pipe progressing at Krishna Nagar road, Peroorkada. Road restoration of PWD BM & BC road in MC road yet to start. Rock breaking and removal ongoing at Peroorkada. Hydrotest water filling yet to start at Kurissady junction-Kusavarkal road, Nalanchira. Thiruvananthapuram Project AE3
27 Feb 2022 Laying of 600mm DI pipe from Karumbumkonam towards Kariyam junction progressing. All culverts in between crossed beneath. 11KV electrical cable crossings identified using KSEBL cable tracing unit. Road restoration work progressing in Kudappanakunnu MLA road. Laying of 1118mm MS pipe progressing in Krishna Nagar road, Peroorkada. Rock breaking and removal of rock started near NPP lane, Peroorkada. Dummy fiixed at both ends for hydrotest of 914mm MS pipe from Kurissady junction to Kusavarkal road. Thiruvananthapuram Project AE3
25 Feb 2022 Laying of 600mm DI pipe from Karumbumkonam junction towards Kariyam junction progressing. 2 culverts crossed beneath. Road restoration work completed upto Kalabasha junction (850m). Laying of 1118mm MS pipe progressing in Krishna Nagar road, Peroorkada. Laying of 914mm MS pipe completed in Kusavarkal road. Preparations for hydrotest ongoing. Road restoration work in progress at PWD road in MLA road, Kudappanakunnu. Thiruvananthapuram Project AE3
21 Feb 2022 Laying of 600mm DI pipe started from Karumbumkonam temple road upto Kariyam junction. Valve chamber construction for air valve of 600mm DI pipe completed at Kalabasha junction. Road restoration work of Corporation road in progress from Karumbumkonam towards VRK road. Laying of 914mm MS pipe in progress at Kusavarkal road. Laying of 1118mm MS pipe in progress at Krishna Nagar road, Peroorkada. Thiruvananthapuram Project AE3