Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Aug 2021 A)1218 mm MS works - (12 m pipe tar coating done-total 144 m of pipe tar coating done ), Pipes laid till date-48 M. (B ) 1118 mm MS works - Total pipes supplied - 792 M ,Pipes laid till date - 830 M.(C)914 mm MS pipe works-Total pipes supplied - 1368 M, Pipes laid till date - 480 M. (D) 813 mm MS works- No progress.(E)711 mm MS-No progress.(F) 600 mm DI - Total pipes supplied - 2165 M, Pipes laid till date - 1201.7 M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
05 Aug 2021 A)1218 mm MS works - (12 m pipe tar coating done-total 144 m of pipe tar coating done ), Pipes laid till date-48 M. (B ) 1118 mm MS works - Total pipes supplied - 684 M ,Pipes laid till date - 710 M.(C)914 mm MS pipe works-Total pipes supplied - 1368 M, Pipes laid till date - 460 M. (D) 813 mm MS works- No progress.(E)711 mm MS-No progress.(F) 600 mm DI - Total pipes supplied - 2165 M, Pipes laid till date - 1185.2 M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
02 Aug 2021 (A)1218mm MS works - (12 m pipe tar coating done-total 144 m of pipe tar coating done ), Total pipes laid till date-48 M. (B ) 1118mm MS works - (576M of pipes supplied till date ,Total pipes laid till date - 560M.(C)914mm MS pipe works-(1368Mof pipes supplied till date, Total pipes laid till date -297M. (D) 813mm MS works- No progress.(E)711mm MS-No progress.(F) 600mm DI - 2165M of pipes supplied till date, Total pipes laid till date - 1147M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
02 Aug 2021 (A)1218mm MS works - (12 m pipe tar coating done-total 144 m of pipe tar coating done ), Total pipes laid till date-48 M. (B ) 1118mm MS works - (576M of pipes supplied till date ,Total pipes laid till date - 560M.(C)914mm MS pipe works-(1368Mof pipes supplied till date, Total pipes laid till date -297M. (D) 813mm MS works- No progress.(E)711mm MS-No progress.(F) 600mm DI - 2165M of pipes supplied till date, Total pipes laid till date - 1147M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
28 Jul 2021 (A)1218mm MS works - (12 m pipe tar coating done-total 144 m of pipe tar coating done ), Total pipes laid till date-48 M. (B ) 1118mm MS works - (576M of pipes supplied till date ,Total pipes laid till date - 560M.(C)914mm MS pipe works-(1368Mof pipes supplied till date, Total pipes laid till date -297M. (D) 813mm MS works- No progress.(E)711mm MS-No progress.(F) 600mm DI - 2165M of pipes supplied till date, Total pipes laid till date - 1147M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
22 Jul 2021 (A).1218mm MS works(12 m pipe tar coating done-total 144 m of pipe tar coating done ;2.laying of pipes-36 m ;(B ) 1118mm MS works(1.504 m of pipes supplied till date ;2.24 m of pipes laid-470 m of pipes laid till date);(C)914mm MS pipe works-(1. 1080 m of pipes supplied till date; 2.–total laid qty-261m). (C) 813mm MS works- No progress;(D)711mm MS-No progress;(E) 600mm DI-(1.2165m of pipes supplied till date;2.1112m of pipes laid till date –pressure testing works in progress). A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force. Thiruvananthapuram Project AE5
20 Jul 2021 (A).1218mm MS works(12m pipe tar coating done-total 96 m of pipe tar coating done ;laying works not started);(B ) 1118mm MS works(1.324 m of pipes supplied till date ;2.18m of pipes laid-440 m of pipes laid till date);(C)914mm MS pipe works-(1. 1080 m of pipes supplied till date; 2.–total laid qty-261m). (C) 813mm MS works- No progress;(D)711mm MS-No progress;(E) 600mm DI-(1.2165m of pipes supplied till date;2.1112m of pipes laid till date –pressure testing works in progress). A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes,appoint more supervisors, increase the work force. Thiruvananthapuram Project AE5
15 Jul 2021 Laying of 18 m of 914mm MS done(235 m laid till date)(from Kudapanakunnu to Madathunada jn); 12 m of tar coating works done in the department supplied 1218mm MS(24 m tar coating done till date) . Laying of Department supplied 1118m MS pipe done -410 m till date. Supply of 72m of 1118mm MS done; Supply of 72m of 914mm MS plain pipes done for making bends; The Supply of 600mm DI is complete - 2165m. Laying is around 50% complete - 1112m. For 914mm MS pipe - 1080 m out of 4415m has been supplied by contractor. The 600mm DI K9 hydraulic pressure testing works in progress. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021.Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, increase the work force. Now pipe laying & tar coating works delaying due to the rain on 14.7.2021 . Thiruvananthapuram Project AE5
12 Jul 2021 Now the works temporarily delaying due to the rain;Laying of supplied 914mm MS pipe done-(181 m till date)(from Kudapanakunnu to Madathunada jn);Laying of Department supplied 1118m MS pipe done -410 m till date. Supply of 72m of 1118mm MS done; Supply of 72m of 914mm MS plain pipes done for making bends; The Supply of 600mm DI is complete - 2165m. Laying is around 50% complete - 1112m. For 914mm MS pipe - 1080 m out of 4415m has been supplied by contractor. The 600mm DI K9 hydraulic pressure testing works in progress. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021.Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, increase the work force. Thiruvananthapuram Project AE5
07 Jul 2021 Laying of supplied 914mm MS pipe is in progress - 157 m till date(from Kudapanakunnu to Madathunada jn);Laying of Department supplied 1118m MS pipe in progress -410 m till date. . The Supply of 600mm DI is complete - 2165m. Laying is around 50% complete - 1112m. For 914mm MS pipe - 1080m out of 4415m has been supplied by contractor. The 600mm DI K9 hydraulic pressure testing works started. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021.Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, increase the work force . Thiruvananthapuram Project AE5