Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Apr 2022 Heavy rain caused delay in pipe laying and rock breaking and removal. Application of chemical for rock breaking could not be done. 6m of 1118mm MS pipe laid, welding and epoxy coating done near NPP Nagar, Lane-1, Peroorkada. Road restoration work completed at Peroorkada-Krishna nagar road upto WMM layer. Thiruvananthapuram Project AE3
19 Apr 2022 Road restoration work ongoing at Peroorkada-Krishna Nagar road. Laying of GSB and WMM layer in progress. Rock breaking and removal for pipe laying ongoing near Church/KWA Compound, Peroorkada for interconnection works to Peroorkada GLSR. Also near NPP Nagar, Lane-1 Peroorkada for laying of 1118mm MS pipe. Laying of remaining 914mm MS pipe (700m) yet to be started at MLA road. Thiruvananthapuram Project AE3
14 Apr 2022 Road restoration work in progress at Peroorkada-Krishna Nagar road. Heavy rain (Yellow alert from last 5 days upto next week) has caused delay in work. Rock breaking and removal in progress at Peroorkada NPP Nagar Lane-1 and near Church KWA (for interconnection work to Peroorkada GLSR). Thiruvananthapuram Project AE3
09 Apr 2022 Construction of 2 nos. of Anchor block for bends at Kurissady junction. Rock breaking near Peroorkada-NPP Nagar progressing. Road restoration work ongoing at Peroorkada-AKG Nagar road. Thiruvananthapuram Project AE3
06 Apr 2022 Rock breaking near Peroorkada NPP Nagar ongoing. Interconnection work to Peroorkada GLSR near Church/KWA Compound ongoing. Anchor block constructed for bend near Kurissady junction, Nalanchira. Thiruvananthapuram Project AE3
05 Apr 2022 Rock breaking near Peroorkada NPP Nagar ongoing. Depth about to acheive for laying 1118mm MS pipe. Road restoration work progressing at Peroorkada-AKG Nagar road upto Krishna Nagar. Interconnection work towards Peroorkada GLSR progressing near KWA compound back side near Church, Peroorkada. Thiruvananthapuram Project AE3
02 Apr 2022 Hydrostatic pressure test conducted successfully for the 525m stretch of 1118mm MS pipe laid on Peroorkada-Krishna Nagar stretch. Road restoration work in progress from Peroorkada towards Krishna Nagar road. Rock breaking and removal in progress. Work of pipe laying and interconnection to Peroorkada GLSR progressing near KWA Compound/Near Church at Peroorkada. Thiruvananthapuram Project AE3
29 Mar 2022 Emulsion spray (SS) sprayed over granular surface at MC road for avoiding dust. WMM layer refilled and trench covering raised at settled portions. Hydrostatic pressure test water filling in progress at 525m stretch of 1118mm MS pipe from Krishna Nagar to Peroorkada NPP nagar. Thiruvananthapuram Project AE3
27 Mar 2022 Road restoration work upto WMM layer completed at VRK-Kariyam road.Road restoration work at PWD road from Peroorkada-AKG Nagar-Kudappanakunnu started. Preparations for hydrostatic pressure test started at 114m reach of 1118mm MS pipe laid at Krishna Nagar road. Rock breaking - more work force engaged at Peroorkada-trench taken extra length for more rock removal. Thiruvananthapuram Project AE3
25 Mar 2022 Road restoration works ongoing in Corporation road at Karumbumkonam-Kariyam stretch. Laying of 600mm DI pipe completed at Karumbumkonam-Kariyam stretch. Preparations of hydrotest ongoing for 520m of 1118mm MS pipe laid from Krishna Nagar to Peroorkada. Rock breaking and removal process using chemical ongoing at Peroorkada. Joining of 914mm MS pipe near Kurissady junction using bends ongoing. Thiruvananthapuram Project AE3