Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Sep 2021 Remarks from SPV given for the observations by KIIFB in Suspension notice issued. Waiting for orders of Suspension revocation, as discussed with KIIFB officials. Meanwhile the portions left uncovered were backfilled and compacted. GSB were filled and compacted in areas where muddy soil and sludge due to rain generated. Contractor arranged team for soil conductivity test and thermoweld connections for Cathodic protection system in MS pipes. Soil conductivity being tested at various locations in the pipe laying route for analysing the possibilites of requirement of Cathodic protection system at different locations.   Thiruvananthapuram Project AE3
18 Sep 2021 Suspension notice issued by KIIFB due to violation of tripartite agreement, vide KIIFB letter no.WRD005-121-05-TIW-PIP-01 dated 14.09.2021 received on 16.09.2021 16:00 hrs Thiruvananthapuram Project AE3
14 Sep 2021 1) 1219mm MS pipe - 150m laid, 220 m pipe supplied departmentally. Tar coating done for 220m. 2)1118mm MS pipe - 1115m pipe laid, 1944m pipe supplied (includes 504m dept. supply). Welding of socket joints/butt joints done and tested (pressure and dye test). 3) 914mm MS pipe - 565.6m pipe laid, 2014.72m pipe supplied. 4)813mm and 711mm MS pipes - No material supplied and laid. 5)600mm DI pipe - 1234m pipe laid, 2161.5m pipe supplied. Issues 1) Due to persistent rain, loose soil and water logging at 600mm DI pipe laying locations, it is not possible to lay the pipe and hydrostatic pressure test is not possible. 2) Hard rock is present at locations of 914mm, 1118mm and some portions of 1219mm MS pipe laying locations, due to which delay is occurring in removing the rock and excavation. 3) Existing pipes and cables underneath are more in 1219mm and 1118mm MS pipe laying locations, and accidental breaking of pipes and cables and their restoring is causing delay in pipe laying. 4) PWD road cutting permission agreement not given by EE, PWD. On enquiry the letter and agreement given was not found in the office and need to be freshly submitted. 5) Corporation road cutting permission agreement also not obtained. On enquiry with zonal office, it was informed that council meeting demanded the charges for road restoration of all stretches, which was pending in the zonal office, and will be submitted this week. Thiruvananthapuram Project AE3
12 Sep 2021 1) 1219mm MS pipe - 82m laid, 232 m pipe supplied departmentally. Tar coating done for 220m. Butt welding of joints and dye test done. 2)1118mm MS pipe - 1012m pipe laid, 1944m pipe supplied (includes 504m dept. supply). Welding of socket joints/butt joints done and tested (pressure and dye test). 3) 914mm MS pipe - 565.6m pipe laid, 2014.72m pipe supplied. 4)813mm and 711mm MS pipes - No material supplied and laid. 5)600mm DI pipe - 1234m pipe laid, 2161.5m pipe supplied. Issues 1) Due to persistent rain, loose soil and water logging at 600mm DI pipe laying locations, it is not possible to lay the pipe and hydrostatic pressure test is not possible. 2) Hard rock is present at locations of 914mm, 1118mm and some portions of 1219mm MS pipe laying locations, due to which delay is occurring in removing the rock and excavation. 3) Existing pipes and cables underneath are more in 1219mm MS pipe laying location, and accidental breaking of pipes and cables and their restoring is causing delay in pipe laying. 4) PWD road cutting permission agreement not given by EE, PWD. On enquiry the letter and agreement given was not found in the office and need to be freshly submitted. 5) Corporation road cutting permission agreement also not obtained. On enquiry with zonal office, it was informed that council meeting demanded the charges for road restoration of all stretches, which was pending in the zonal office, and will be submitted this week. Thiruvananthapuram Project AE3
08 Sep 2021 1) 1219mm MS pipe - 64m laid, 232 m pipe supplied departmentally. Tar coating done for 220m. Butt welding of joints and dye test done. 2)1118mm MS pipe - 993m pipe laid, 1944m pipe supplied (includes 504m dept. supply). Welding of socket joints and pressure testing done. 3) 914mm MS pipe - 565.6m pipe laid, 2014.72m pipe supplied. 4)813mm and 711mm MS pipes - No material supplied and laid. 5)600mm DI pipe - 1234m pipe laid, 2161.5m pipe supplied. Issues 1) Due to rain, loose soil and water logging at 600mm DI pipe laying locations, it is not possible to lay the pipe and hydrostatic pressure test is not possible. 2) Hard rock is present at locations of 914mm and 1118mm MS pipe laying locations, due to which delay is occurring in removing the rock and excavation. 3) Existing pipes and cables underneath are more in 1219mm MS pipe laying location, and accidental breaking of pipes and cables and their restoring is causing delay in pipe laying. Thiruvananthapuram Project AE3
08 Sep 2021 1) 1219mm MS pipe - 64m laid, 232 m pipe supplied departmentally. Tar coating done for 220m. Butt welding of joints and dye test done. 2)1118mm MS pipe - 964m pipe laid, 1944m pipe supplied (includes 504m dept. supply). Welding of socket joints done pressure testing done. 3) 914mm MS pipe - 565.6m pipe laid, 2014.72m pipe supplied. 4)813mm and 711mm MS pipes - No material supplied and laid. 5)600mm DI pipe - 1234m pipe laid, 2161.5m pipe supplied. Issues 1) Due to rain, loose soil and water logging at 600mm DI pipe laying locations, it is not possible to lay the pipe and hydrostatic pressure test is not possible. 2) Hard rock is present at locations of 914mm and 1118mm MS pipe laying locations, due to which delay is occurring in removing the rock and excavation. 3) Existing pipes and cables underneath are more in 1219mm MS pipe laying location, and accidental breaking of pipes and cables and their restoring is causing delay in pipe laying. Thiruvananthapuram Project AE3
05 Sep 2021 A)1218 mm MS works - (12 m pipe tar coating done-total 220 m of pipe tar coating done ), Pipes laid till date - 61m, Testing (DP) of butt weld joints done for 4 bend joints. (B ) 1118 mm MS works - Total pipes supplied - 1944m, includes dept. supply - 504m ,Pipes laid till date - 993m, (C)914 mm MS pipe works-Total pipes supplied - 2014.72m, Pipes laid till date - 565.6 M. (D) 813 mm MS works- No progress.(E)711 mm MS-No progress.(F) 600 mm DI - Total pipes supplied - 2165 M, Pipes laid till date - 1234m. Laying of 600mm DI pipe is facing issues due to rain and loose soil at the location. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 07/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
25 Aug 2021 A)1218 mm MS works - (12 m pipe tar coating done-total 220 m of pipe tar coating done ), Pipes laid till date-48 M. (B ) 1118 mm MS works - Total pipes supplied - 1008 M ,Dept. supply - 504 M ,Pipes laid till date - 945.5 M.(C)914 mm MS pipe works-Total pipes supplied - 1726.7 M, Pipes laid till date - 565.6 M. (D) 813 mm MS works- No progress.(E)711 mm MS-No progress.(F) 600 mm DI - Total pipes supplied - 2165 M, Pipes laid till date - 1201.7 M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3
25 Aug 2021 72 m of 1100 and 216 m of 900 supplied on 23 rd August Thiruvananthapuram Proj Dn AEE 2
14 Aug 2021 A)1218 mm MS works - (12 m pipe tar coating done-total 144 m of pipe tar coating done ), Pipes laid till date-48 M. (B ) 1118 mm MS works - Total pipes supplied - 792 M ,Pipes laid till date - 830 M.(C)914 mm MS pipe works-Total pipes supplied - 1368 M, Pipes laid till date - 480 M. (D) 813 mm MS works- No progress.(E)711 mm MS-No progress.(F) 600 mm DI - Total pipes supplied - 2165 M, Pipes laid till date - 1201.7 M. A letter has been served to Contractor dt 31/5/2021 asking him to supply the required balance MS pipes immediately as committed in the meeting held by Superintending Engineer on 7/05/2021. Also on 1.7.2021 ,a meeting conducted in the chamber of Superintending Engineer & directions given to contractor to supply the balance pipes, appoint more supervisors, increase the work force etc. Thiruvananthapuram Project AE3