Status Date Overall Project Status Project Officer Contact
21 Jan 2022 Road restoration work in progress at Kudappanakunnu-Krishna Nagar road. Hydrostatic pressure test completed successfully for 600mm DI pipe at VRK junction-Kalabhash stretch. Preparations for hydro test ongoing at 914mm MS pipe laid at MC road from AMSET to Kurissady junction, MC road. 1118mm MS pipe - 24 m laid at Peroorkada junction, where the rock was found and removed. Thiruvananthapuram Project AE3
18 Jan 2022 Road restoration work ongoing at Kudappanakunnu-Krishna Nagar road. Levels of road restoration completed at Kudappanakunnu-Pathirapally-Madathunada road and MC road from AMSET to Kurissady junction. Laying of 914mm MS pipe progressing at Nalanchira Kusavarkal road. Thiruvananthapuram Project AE3
12 Jan 2022 Road restoration work progressing at Kudappanakunnu-Krishna Nagar road. Hydrostatic pressure test - pressure application on 600mm DI pipe started. Laying of 914mm MS pipe at MC road, Nalanchira completed upto Kurissady junction. Length of pipe laid - 613.75m. Welding of joints and coating completed for the pipes laid at Kusavarkal road, Nalanchira. Thiruvananthapuram Project AE3
10 Jan 2022 Road restoration work progressing at Kudappanakunnu-Krishna Nagar road. Anchor block construction and pipe laying progressing at MC road, Nalanchira towards Kurissady junction. 570m out of 700m pipe laid in the stretch. Welding of joints and tar coating works in progress. Thiruvananthapuram Project AE3
09 Jan 2022 Road restoration work at Kudappanakunnu-KrishnaNagar road started and progressing. Work of laying 914mm MS pipe progressing at MC road towards Kurissady junction. 506m of pipe laid out of 700m till date. The work of laying 914mm MS pipe progressing at Nalanchira Kusavarkal road. The preparation for hydrostatic pressure test, viz fixing dummy plates etc. ongoing at VRK junction-Karumbumkonam road (600mm DI pipe location). Thiruvananthapuram Project AE3
06 Jan 2022 Laying of 914mm MS pipe progressing at MC road and Kusavarkal road. 500m out of 700m pipe laid at MC road towards Kurissady junction. Hydrostatic pressure test preparations ongoing for 600mm DI pipe laid. Road restoration work from Kudappanakunnu towards Krishna Nagar road started. Thiruvananthapuram Project AE3
02 Jan 2022 Laying of 914mm MS pipe progressing at MC road, near Nalanchira. 493m out of 700m upto Nalanchira Kurissady junction laid till date. Pressure testing of weld joints and tar coating ongoing. 914mm MS pipe laying commenced at Nalanchira Kusavarkal road. 12m of pipe laid. Thiruvananthapuram Project AE3
31 Dec 2021 914mm MS pipe laying ongoing at MC road, near Nalanchira. Welding of joints (socket and butt weld joints) ongoing along with coal tar epoxy coating on exterior. 448m out of 700m pipe laid till date. Dummy plates for conducting hydrostatic pressure test at Kusavarkal road constructed. Rock cutting ongoing at Kudappanakunnu MLA road and Peroorkada-Krishna Nagar road. Thiruvananthapuram Project AE3
30 Dec 2021 Rock breaking and removal process ongoing at 914mm MS pipe laying location (MLA road, Kudappanakunnu) and 1118mm MS pipe laying location (at Peroorkada-Krishna Nagar road). Laying of 914mm MS pipe at MC road, Near Nalanchira Kurissady junction ongoing. 430m pipe laid out of 700m till date. Thiruvananthapuram Project AE3
29 Dec 2021 Laying on 914mm MS pipe ongoing at MC road, Nalanchira. Total of 420.33 m of pipe laid till date. Rock breaking and removal process ongoing. Preparation for conducting hydrostatic pressure test ongoing at Nalanchira Kusavarkal road for 914mm MS pipe laid. Thiruvananthapuram Project AE3