Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Oct 2021 914 x 30 degree MS bend and 6m of 914mm MS pipe laid at Nalanchira-Kusavarkal road. Pressure test of 2 nos of socket joints done. Valve chamber construction completed at two locations - 914mm air valve location near Madathunada, and 1118mm air valve location near Marygiri School, Kudappanakunnu. 6m of 1118mm MS pipe laid near AKG Nagar, Peroorkada. Thiruvananthapuram Project AE3
25 Oct 2021 At 914mm MS pipe laying location near Kurissady, Nalanchira....a crossing of Jio OFC cable was found at a depth of 1.3-1.5m and due to which pipe laying at min depth of 1m was not possible which lead to obstruction of work. After informing Jio Fiber Engineer and team, under their supervision, trench taken without damage to cables and 6m of 914mm MS pipe laid. Thiruvananthapuram Project AE3
22 Oct 2021 Due to the unexpected land slide near AKG Nagar, Peroorkada of 1118mm MS pipe laying location, laying work not done. Welding of joints done and tested for laid pipes. Instructed to provide pile and side shoring before further laying of pipes at the location. 914mm MS pipe socket joints welded and pressure test done @ Nalanchira. Thiruvananthapuram Project AE3
19 Oct 2021 Laying of 1118mm MS pipes - 12m laid near AKG Nagar. Preparations including identification of underground cables etc. at 914mm MS pipe laying location near Nalanchira completed. Laying to commence from 20.10.2021. Thiruvananthapuram Project AE3
15 Oct 2021 Hydrostatic pressure tests conducted successfully on 1219mm MS pipe -186.25m, 1118mm MS pipe - 972.2m and 914mm - 523m. Laying of 1118mm MS pipes near Krishna nagar road - 24m laid Thiruvananthapuram Project AE3
12 Oct 2021 Received the suspension revocation notice from KIIFB PFMS portal at 17 hrs on 12.10.2021. Informed contractor regarding the notice and instructed to start the work immediately. Thiruvananthapuram Project AE3
12 Oct 2021 Received the suspension revocation notice from KIIFB officially at 17 hrs on 12.10.2021. Informed contractor regarding the notice and instructed to start the work immediately. Thiruvananthapuram Project AE3
11 Oct 2021 Got information from KIIFB that the suspension revocation file has got approval. Yet to receive the orders officially. Thiruvananthapuram Project AE3
04 Oct 2021 Oral clarifications on the reply of Suspension notice submitted to KIIFB were given over phone. Waiting for suspension revocation orders from KIIFB. Thiruvananthapuram Project AE3
29 Sep 2021 Advance copy of remarks from SPV for the observations by KIIFB in Suspension notice sent to KIIFB on 27.09.21. Waiting for orders of Suspension revocation, as discussed with KIIFB officials. Meanwhile the portions left uncovered were backfilled and compacted. GSB were filled and compacted in areas where muddy soil and sludge due to rain generated. Thiruvananthapuram Project AE3