Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Feb 2022 Hon MLA, Vattiyoorkavu Constituency, Councillor - Peroorkada, Pathirappally wards, SE, KWA PH Circle, Tvpm, EE, Project Div, visited the work site at KrishnaNagar road, Kudappanakunnu. Hon MLA advised to complete the pipe laying work at Peroorkada-AKG Nagar-KrishnaNagar road at the earliest and insisted to start of road restoration works at the above stretch inorder to avoid public complaints. Also visited MLA road, Kudappanakunnu and advised to complete the road restoration work at MLA road at the earliest, so as to avoid complaints from public and to make the commutation through the road easier. Thiruvananthapuram Project AE3
15 Feb 2022 Laying of 1118mm MS pipe in progress at Krishna Nagar road, Peroorkada. Due to heavy rain, surrounding tarred road surface slided into trench despite providing side shutters since the said portion is a low lying area. The welding works of laid pipes in Nalanchira Kusavarkal road ongoing. The problem of sliding of surrounding earth surface inside trenches due to loose soil in the area and low lying area. Road restoration works initial levels reported to KIIFB for starting RR works at VRK-Karumbumkonam road where 600mm DI pipe laid and tested. Thiruvananthapuram Project AE3
12 Feb 2022 Bitumen emulsion (RS) tack coat sprayed on Kudappanakunnu-Krishna Nagar road, where gsb and wmm laid and rolled. Laying of 914mm MS pipe in progress at Nalanchira Kusavarkal and 1118mm MS pipe laying at Krishna Nagar road. Culvert constructed at Krishna Nagar road, where 1118mm MS pipe laid below culvert. Thiruvananthapuram Project AE3
09 Feb 2022 Laying of 1118mm MS pipe laying at Kudappanakunnu-Krishna Nagar road is in progress. Surrounding earth fallen into trench at the location due to loose soil and water from inside trenches. Instructed contractor to provide side shutters with sufficient depth and width. Laying of 914mm MS pipe in progress at Kusavarkal road. Surrounding trench falling due to loose soil at the area and underlying trench water in low lying area. Valve chamber construction completed at Peroorkada and Kurissady junction. Rock breaking in progress at Peroorkada. Road restoration work to be started at MC road and VRK-Karumbumkonam road. Thiruvananthapuram Project AE3
06 Feb 2022 Laying of 914mm MS pipe across culvert done at Nalanchira Kusavarkal road. Surrounding earth slided into trench over side shoring due to loose soil and ground water oozing out from trenches due to low lying area. Welding of joints carried out by pumping out of water at the location. 1118mm MS pipe laying at Krishna Nagar road progressing, culvert crossing done and further laying progressing. Valve chamber construction in progress at Nalanchira Kurissady junction and Peroorkada. Thiruvananthapuram Project AE3
03 Feb 2022 Laying of 914mm MS pipe across culvert in progress at Nalanchira Kusavarkal road. Laying of 1118mm MS pipe in Krishna Nagar road started. Pipe to be laid across culvert near by. Rock breaking and removal in progress near Peroorkada GLSR compound in progress. Valve chamber construction in progress at Nalanchira Kurissady junction and Peroorkada. Thiruvananthapuram Proj Dn AEE 2
02 Feb 2022 Laying of 914mm MS pipe at Nalanchira Kusavarkal road - culvert crossing of pipe in progress. Due to low lying area and ground water oozing out from trenches, work is getting delayed. Hydrostatic pressure test conducted successfully for 872m of 600mm DI pipe from Kalabasha gardens jn upto Karumbumkonam junction. Rock breaking and removal in progress near Peroor Hospital, Peroorkada. Thiruvananthapuram Project AE3
01 Feb 2022 Laying of 914mm MS pipe at Nalanchira Kusavarkal road - culvert crossing of pipe in progress. Due to low lying area and ground water oozing out from trenches, work is getting delayed. Hydrostatic pressure test conducted successfully for 872m of 600mm DI pipe from Kalabasha gardens jn upto Karumbumkonam junction. Thiruvananthapuram Project AE3
28 Jan 2022 Laying of 914mm MS pipe in progress at Nalanchira Kusavarkal road. Rock cutting and removal in progress at Kudappanakunnu MLA road and Peroorkada-AKG Nagar road. Hydrostatic pressure test started at 2nd stretch of 600mm DI pipe near Karumbumkonam. Thiruvananthapuram Project AE3
24 Jan 2022 Hydrostatic pressure test conducted successfully for 613mm of 914mm MS pipe laid at MC road (Kurissady junction to AMSET junction). Anchor block (3 nos) constructed at 600mm DI pipe laid near Karumbumkonam junction. Laying of 914mm MS pipe in progress near Kusavarkal road. Thiruvananthapuram Project AE3