Status Date Overall Project Status Project Officer Contact
28 Dec 2021 Rock breaking in progress at Kudappanakunnu MLA road (914mm MS pipe laying location), Depth attained is almost 2m. Need 0.25m more depth for laying and side removal required for welding etc. Rock breaking in progess at Peroorkada-AKG Nagar road, depth attained just above 2m on average. Need removal of rock at sides. Laying of 914mm MS pipe in progresss at MC road, near Nalanchira, 24m pipe laid. 390m laid till date. Thiruvananthapuram Project AE3
26 Dec 2021 Laying of 914mm MS pipe in progress near Nalanchira, MC Road. 369.33m of pipe laid till date. Dye Penetrant testing and pressure testing of welded joints ongoing. Epoxy coating on exterior weld joints and cement lining on internal weld joints ongoing. 2 nos. of Anchor block constructed near Nalanchira Mar Ivanios Nagar. Thiruvananthapuram Project AE3
22 Dec 2021 Laying of 914mm MS pipe near Nalanchira MC road in progress. 48.7m of pipe laid yesterday and day before. Total of 345.33m of pipe laid till date at MC road. Welding of joints, testing and outer/inner coating on joints ongoing simultaneously. Thiruvananthapuram Project AE3
19 Dec 2021 Laying of 914mm MS pipe in progress near Nalanchira MC Road.49.05m of pipe laid yesterday night. Total pipe laid till date from AMSET junction towards Kurissady junction, Nalanchira out of 700m is 266.15m. Rock breaking at Peroorkada in progress. Thiruvananthapuram Project AE3
16 Dec 2021 Laying of 914mm MS pipe at MC road near Nalanchira in progress. 175m pipe laid till date. Pipe laying in Kurissady-Kusavarkal road in progress. 372 m of 914mm MS pipe laid till date. Welding and testing of joints and tar coating of joints in progress. Rock breaking near Peroorkada site in progress. Thiruvananthapuram Project AE3
12 Dec 2021 KIIFB Technical Inspection wing has visited the work sites at Peroorkada, Nalanchira Kusavarkal road and MC road, Paruthipara on 10/12/21. Inspected in detail about the physical progress of work at the various locations. 32m of 914mm MS pipe laid at MC road near Nalanchira Mar Ivanios junction. Culvert which was on the pipe laying alignment at 2.5m depth, pipe was laid below 1.5m depth at culvert base. At Nalanchira-Kusavarkal road, the road was levelled and compacted with GSB layer and 12m of 914mm MS pipe laid. Thiruvananthapuram Project AE3
09 Dec 2021 Work of laying 914mm MS pipe started at Amset Centre junction, Nalanchira. 82m of pipe laid. Welding of joints and pressure testing in progress. 12m of 914mm MS pipe laid at Kusavarkal road, Nalanchira. 362m of 914mm MS pipe laid till date at Kusavarkal road, Nalanchira. Welding, pressure testing and epoxy coating and cement lining of joints in progress. Thiruvananthapuram Project AE3
05 Dec 2021 12m of 914mm MS pipe laid at Kusavarkal road, Nalanchira. Damaged and broken AC pipe replaced with PVC and joints were connected. Welding of joints and testing on joints done. Thiruvananthapuram Project AE3
04 Dec 2021 Hon MLA, Vattiyoorkavu Constituency visited the site at Peroorkada and MLA road, Kudappanakunnu on 02/12/21. Advised to backfill the open trenches at Peroorkada inorder to facilitate smooth public commutation. Also told to take necessary steps for speeding up rock breaking and removal and road restoration works. Compacting and levelling of mud portions done using compacting machine and made the road more suitable for public transport. 914mm MS pipe laying at Nalanchira Kusavarkal started and progressing. Welding of joints, weld testing and epoxy coating on welded joints done. Thiruvananthapuram Project AE3
01 Dec 2021 MD, KWA visited the work site near AKG Nagar on 30.11.2021, Peroorkada and instructed to complete the road restoration works urgently. Also gave instructions to the contractor for supplying the balance pipes at the earliest for the laying of pipes at remaining locations. To speed up the rock breaking, removal and the site need to be cleared for public commutation after completing the work immediately. MD insisted that the work progress is slow and balance work to be completed within the extended time period granted. Thiruvananthapuram Project AE3