Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given. Thrissur PH Dn EE
05 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
03 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
30 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
26 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
23 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
22 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
20 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 122 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
19 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 115 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 54 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
18 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 115 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE