Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Jan 2024 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given. |
Thrissur PH Dn EE |
|
05 Jan 2024 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
03 Jan 2024 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
30 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
26 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
23 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
22 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
20 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 122 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
19 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 115 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 54 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
18 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 115 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|