Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
27 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
26 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
26 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 93 FHTCs given , Part C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
25 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 93 FHTCs given , Part C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
14 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 93 FHTCs given , Part C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
11 Mar 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 93 FHTCs given , Part C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur WW Sn - AE 1 |
|
07 Mar 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
05 Mar 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur WW Sn - AE 1 |
|
02 Mar 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|