Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Feb 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur WW Sn - AE 1 |
|
28 Feb 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
26 Feb 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur WW Sn - AE 1 |
|
24 Feb 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
21 Feb 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur PH Dn EE |
|
19 Feb 2024 |
Pkg A- 100% work completed. Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur WW Sn - AE 1 |
|
15 Feb 2024 |
Pkg A-100% work completed.Bill under preparation, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress..63% . Pkg D-33%-Pipe laying and connection work in progress. 33 FHTCs given. |
Thrissur WW Sn - AE 1 |
|
14 Feb 2024 |
Pkg A-58% Pipe laying completed. Connection work in progress. 175 Connections completed, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given |
Thrissur PH Dn EE |
|
12 Feb 2024 |
Pkg A-58% Pipe laying completed. Connection work in progress. 175 Connections completed, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given |
Thrissur WW Sn - AE 1 |
|
09 Feb 2024 |
Pkg A-58% Pipe laying completed. Connection work in progress. 174 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given |
Thrissur PH Dn EE |
|