Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress | Thrissur PH Dn EE | |
20 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress | Thrissur PH Dn EE | |
19 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress | Thrissur PH Dn EE | |
18 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying complete , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
17 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying complete , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
16 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying complete , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
14 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
11 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
10 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
09 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur WW Sn - AE 1 |