Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 106 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
14 Dec 2023 |
Pkg A-57% Pipe laying completed. Connection work in progress. 88 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
13 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress. 73 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given |
Thrissur PH Dn EE |
|
11 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress. 59 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 18 FHTCs Given |
Thrissur PH Dn EE |
|
08 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress. 49 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 18 FHTCs Given |
Thrissur PH Dn EE |
|
07 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress. 39 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 18 FHTCs Given |
Thrissur PH Dn EE |
|
05 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress. 39 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 16 FHTCs Given |
Thrissur PH Dn EE |
|
02 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 16 FHTCs Given |
Thrissur PH Dn EE |
|
02 Dec 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
29 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|