Status Date Overall Project Status Project Officer Contact
16 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 106 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
14 Dec 2023 Pkg A-57% Pipe laying completed. Connection work in progress. 88 Connections given, Pkg B-63% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
13 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress. 73 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given Thrissur PH Dn EE
11 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress. 59 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 18 FHTCs Given Thrissur PH Dn EE
08 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress. 49 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 18 FHTCs Given Thrissur PH Dn EE
07 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress. 39 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 18 FHTCs Given Thrissur PH Dn EE
05 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress. 39 Connections given, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 16 FHTCs Given Thrissur PH Dn EE
02 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress. 16 FHTCs Given Thrissur PH Dn EE
02 Dec 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur PH Dn EE
29 Nov 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur PH Dn EE