Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
06 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
05 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
03 Oct 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 60 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
30 Sep 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 60 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
29 Sep 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 60 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
27 Sep 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied | Thrissur PH Dn EE | |
26 Sep 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
25 Sep 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
23 Sep 2023 | Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE |