Status Date Overall Project Status Project Officer Contact
07 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
06 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
05 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 72 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
03 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 60 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
30 Sep 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 60 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
29 Sep 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 60 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
27 Sep 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-Pipe Supplied Thrissur PH Dn EE
26 Sep 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-survey work in progress Thrissur PH Dn EE
25 Sep 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-survey work in progress Thrissur PH Dn EE
23 Sep 2023 Pkg A-35% Connection work in progress, Pkg B-43% -Pipe laying - work in progress , Pkg C- 59 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-survey work in progress Thrissur PH Dn EE