Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 48 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
27 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
25 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
23 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
22 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
16 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
15 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
14 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
13 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-52% Pipe laying completed, tagging work in progress. 41 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
10 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 32 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|