Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
17 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
15 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
12 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
11 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
09 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
08 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
06 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
04 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
03 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE