Status Date Overall Project Status Project Officer Contact
09 Nov 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 32 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur WW Sn - AE 1
07 Nov 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 32 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur PH Dn EE
06 Nov 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 18 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur PH Dn EE
02 Nov 2023 Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 7 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur WW Sn - AE 1
01 Nov 2023 Pkg A-50% Pipe laying completed, tagging work in progress. 7 FHTCs given, Pkg B-51% -Pipe laying completed ,Connection work in progress Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress Thrissur PH Dn EE
30 Oct 2023 Pkg A-50% Pipe laying completed, Pkg B-51% -Pipe laying completed , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-3%-Pipe laying and connection work in progress Thrissur PH Dn EE
28 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress Thrissur PH Dn EE
27 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress Thrissur PH Dn EE
26 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress Thrissur PH Dn EE
25 Oct 2023 Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress Thrissur PH Dn EE