Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 32 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur WW Sn - AE 1 |
|
07 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 32 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
06 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 18 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
02 Nov 2023 |
Pkg A-50% Pipe laying completed. Connection work in progress, Pkg B-Pipe laying completed, tagging work in progress. 7 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress
|
Thrissur WW Sn - AE 1 |
|
01 Nov 2023 |
Pkg A-50% Pipe laying completed, tagging work in progress. 7 FHTCs given, Pkg B-51% -Pipe laying completed ,Connection work in progress Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-6%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
30 Oct 2023 |
Pkg A-50% Pipe laying completed, Pkg B-51% -Pipe laying completed , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.-63%. Pkg D-3%-Pipe laying and connection work in progress |
Thrissur PH Dn EE |
|
28 Oct 2023 |
Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress |
Thrissur PH Dn EE |
|
27 Oct 2023 |
Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress |
Thrissur PH Dn EE |
|
26 Oct 2023 |
Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress |
Thrissur PH Dn EE |
|
25 Oct 2023 |
Pkg A-35% Connection work in progress, Pkg B-50% -Pipe laying completed , Pkg C- 75 FHTCs given. Pipe laying - work completed. Connection work in progress -62%. Pkg D-1%-pipe laying- work in progress |
Thrissur PH Dn EE |
|