Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2024 Pkg A-58% Pipe laying completed. Connection work in progress. 174 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur WW Sn - AE 1
07 Feb 2024 Pkg A-58% Pipe laying completed. Connection work in progress. 174 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 93 FHTCs given , Pkg C- 96 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur PH Dn EE
06 Feb 2024 Pkg A-58% Pipe laying completed. Connection work in progress. 174 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur PH Dn EE
02 Feb 2024 Pkg A-58% Pipe laying completed. Connection work in progress. 174 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur WW Sn - AE 1
01 Feb 2024 Pkg A-58% Pipe laying completed. Connection work in progress. 174 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur PH Dn EE
29 Jan 2024 Pkg A-58% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur WW Sn - AE 1
22 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given Thrissur WW Sn - AE 1
17 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given. Thrissur PH Dn EE
13 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 33 FHTCs Given. Thrissur PH Dn EE
10 Jan 2024 Pkg A-57% Pipe laying completed. Connection work in progress. 129 Connections given, Pkg B-55% Pipe laying completed, tagging work in progress. 62 FHTCs given , Pkg C- 75 FHTCs given. pipe laying- work completed. Connection work in progress.63% . Pkg D-6%-Pipe laying and connection work in progress. 29 FHTCs Given. Thrissur PH Dn EE