Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
06 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
04 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
02 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
30 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
29 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
27 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
25 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
23 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
22 Apr 2024 Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE