Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
06 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
04 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
02 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
30 Apr 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
29 Apr 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
27 Apr 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
25 Apr 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
23 Apr 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
22 Apr 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 100% Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|