Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
21 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
18 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
17 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
16 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
15 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
14 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
13 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
10 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE
09 May 2024 Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. Thrissur PH Dn EE