Status Date |
Overall Project Status |
Project Officer |
Contact |
23 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
21 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
18 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
17 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
16 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
15 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
14 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
13 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
10 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
09 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|