Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Jun 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 213 FHTC given .pipe laying completed. First part bill paid. second and final under preparation by AE. Part C- 213 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress.10km pipe laying work done. work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
07 Jun 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 213 FHTC given .pipe laying completed. First part bill paid. second and final under preparation by AE. Part C- 213 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress.10km pipe laying work done. work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
06 Jun 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 213 FHTC given .pipe laying completed. First part bill paid. second and final under preparation by AE. Part C- 213 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress.10km pipe laying work done. work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
05 Jun 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 213 FHTC given .pipe laying completed. First part bill paid. second and final under preparation by AE. Part C- 213 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress.10km pipe laying work done. work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
30 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- 213 FHTC given .pipe laying completed. First part bill paid. second and final under preparation by AE. Part C- 213 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress.10km pipe laying work done. work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
29 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
28 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
28 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
27 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|
24 May 2024 |
Part A- 100% work completed. Bill under preparation, Part B- Pipe laying completed, tagging work in progress. 148 FHTCs given , Part C- 151 FHTCs given. pipe laying- work completed. Connection work in progress..70% . Part D-33%-Pipe laying and connection work in progress. 58 FHTCs given. |
Thrissur PH Dn EE |
|