Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 package 1 :Work in progress | 90% Completed | 23/04/2024 350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work package 3 Work in progress | 93% Completed | 23/04/2024 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara package 2 Not Started | 23/04/2024 WORK Arranged in JJM SCHEME ,Estimate submitted for TS approva package 4 Not Started | 23/04/2024 WORK NOT STARTED package 5 Work in progress | 97% Completed | 23/04/2024 THE WORK IS FORE CLOSED Chittur Project Dn - AE 2
11 Apr 2024 Work in progress | 93% Completed | 11/04/2024 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Chittur Project Dn - AE 2
11 Apr 2024 Work in progress | 90% Completed | 11/04/2024 350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Chittur Project Dn - AE 2
15 Feb 2024 PACK-1 Work in progress | 90% Completed | 15/02/2024 350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work PACK-2 Not Started | 15/02/2024 WORK Arranged in JJM SCHEME ,Estimate submitted for TS approval PACK3 Work in progress | 93% Completed | 15/02/2024 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-4 Not Started | 15/02/2024 WORK NOT STARTED Chittur Project Dn - AE 2
29 Nov 2023 Pack-2 Not Started | 29/11/2023 WORK Arranged in JJM SCHEME ,Estimate submitted for TS approval Pack-1 Work in progress | 90% Completed | 29/11/2023 350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-3 Work in progress | 93% Completed | 29/11/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 29/11/2023 WORK NOT STARTED Chittur Project Dn - AE 2
03 Nov 2023 Pack-1 350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-2 Not Started | 03/11/2023 work tendered several times nobody participated, work arranged in JJM pack-3 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 03/11/2023 WORK NOT STARTED Pack-5 Work fore closed Chittur Project Dn - AE 2
13 Oct 2023 Pack-1 Work in progress | 90% Completed | 13/10/2023 350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work PACK-2 Not Started | 13/10/2023 work tendered several times nobody participated, work arranged in JJM PACK-3 Work in progress | 93% Completed | 13/10/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-4 Not Started | 13/10/2023 WORK NOT STARTED Chittur Project Dn - AE 2
28 Sep 2023 Pack-1 Work in progress | 90% Completed | 28/09/2023 Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-2 Not Started | 28/09/2023 work tendered several times nobody participated pack-3 Work in progress | 93% Completed | 28/09/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 28/09/2023 WORK NOT STARTED Pack-5 Work for closed Chittur Project Dn - AE 2
07 Sep 2023 Pack-1 Work in progress | 90% Completed | 07/09/2023 Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-2 Not Started | 07/09/2023 work tendered several times nobody participated pack-3 Work in progress | 93% Completed | 07/09/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 07/09/2023 WORK NOT STARTED pack-5 work foreclosed on 24.08.2022 Chittur Project Dn - AE 2
12 Aug 2023 Pack-1 Work in progress | 90% Completed | 12/08/2023 Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-2 Not Started | 12/08/2023 work tendered several times nobody participated pack-3 Work in progress | 93% Completed | 12/08/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 12/08/2023 WORK NOT STARTED pack-5 work foreclosed on 24.08.2022 Chittur Project Dn - AE 2