Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jan 2022 Pack-1 Work in progress | 37% Completed | 25/01/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 25/01/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 47% Completed | 25/01/2022 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- floor beam and floor slab concrete work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6800.00m laid 250mm DI K9 -1540M SUPPLIED 400 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 22% Completed | 25/01/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 88% Completed | 25/01/2022 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72831.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3154 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-54M TOTAL – 83.601KM Chittur Project Dn - AE 2
20 Jan 2022 Pack-1 Work terminated | 37% Completed | 20/01/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 20/01/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 47% Completed | 20/01/2022 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- floor beam and floor slab form work and reinforcement work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6800.00m laid 250mm DI K9 -1540M SUPPLIED 400 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 22% Completed | 20/01/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 88% Completed | 20/01/2022 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72831.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3154 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-54M TOTAL – 83.601KM Chittur Project Dn - AE 2
12 Jan 2022 Pack-1 Work in progress | 37% Completed | 12/01/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 12/01/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 46% Completed | 12/01/2022 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- floor beam and floor slab form work and reinforcement work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6800.00m laid 250mm DI K9 -1540M SUPPLIED 400 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 22% Completed | 12/01/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 87% Completed | 12/01/2022 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72831.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3154 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-54M TOTAL – 83.601KM Chittur Project Dn - AE 2
10 Jan 2022 Pack-1 Work in progress | 37% Completed | 10/01/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 10/01/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 46% Completed | 10/01/2022 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – plinth beam concrete work complete and above column work in progress 3.) 11.50 LL OHSR -Cherad OHSR- column UP TO FLOOR BEAM completed balance work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6400.00m laid 250mm DI K9 -1540M SUPPLIED , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 22% Completed | 10/01/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 87% Completed | 10/01/2022 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72117.00M 2)110mm pvc,6kg/cm2 – 1334m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2276 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-36M TOTAL – 82.600KM Chittur Project Dn - AE 2
02 Jan 2022 PACK-1 Work in progress | 37% Completed | 02/01/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. PACK-2 Not Started | 02/01/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date PACK-3 Work in progress | 46% Completed | 02/01/2022 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – plinth beam concrete work complete and above column work in progress 3.) 11.50 LL OHSR -Cherad OHSR- column UP TO FLOOR BEAM completed balance work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6400.00m laid 250mm DI K9 -1540M SUPPLIED , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid PACK-4 Work in progress | 22% Completed | 02/01/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 PACK-5 Work in progress | 87% Completed | 02/01/2022 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72117.00M 2)110mm pvc,6kg/cm2 – 1334m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2276 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-36M TOTAL – 82.600KM Chittur Project Dn - AE 2
28 Dec 2021 Pack-1 Work in progress | 36% Completed | 28/12/2021 11 LL OHSR at JTS – Columns upto 4th brace beam completed. 2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR—Third brace shuttering work completed at Padalikkad 4) Malampuzha pump house- column footings completed Pack-2 Not Started | 28/12/2021 In this case, more discussion is required, After discussions, The meeting decided to reach an appropriate decision. As per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-3 Work in progress | 46% Completed | 28/12/2021 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – plinth beam concrete work complete and above column work in progress 3.) 11.50 LL OHSR -Cherad OHSR- column UP TO FLOOR BEAM completed balance work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6400.00m laid 250mm DI K9 -1540M SUPPLIED , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 22% Completed | 28/12/2021 Revised estimate as per latest DSR 2018 is under preparation for approval of PRICE escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.20 Pack-5 Work in progress | 87% Completed | 28/12/2021 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72117.00M 2)110mm pvc,6kg/cm2 – 1334m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2276 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-36M TOTAL – 82.600KM Chittur Project Dn - AE 2
21 Dec 2021 Pack-1 Work in progress | 35% Completed | 21/12/2021 PACK-1 1). 11 LL OHSR at JTS – column above 3RD BRACE shuttering and reinforcement work in progress at JTS Marutharoad 2). 8LL OHSR - Columns above 4th brace casting work completed and floor slab shuttering work progress at Malampuzha and pump house- column footing work in progress 3). 7LL OHSR—Third brace shuttering work in progress at Padalikkad Pack-2 Not Started | 21/12/2021 PIPE LINE LAID FOR A LENGTH OF 44.00 KM Pack-5 Work in progress | 87% Completed | 21/12/2021 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72117.00M 2)110mm pvc,6kg/cm2 – 1334m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2276 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-36M TOTAL – 82.600KM pack-4 Work in progress | 21% Completed | 21/12/2021 Revised estimate as per latest DSR 2018 is under preparation for approval of PRICE escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.202 Chittur Project Dn - AE 2
19 Dec 2021 PACK-1 Work in progress | 35% Completed | 19/12/2021 PACK-1 1). 11 LL OHSR at JTS – column above 3RD BRACE shuttering and reinforcement work in progress at JTS Marutharoad 2). 8LL OHSR - Columns above 4th brace casting work completed and floor slab shuttering work progress at Malampuzha and pump house- column footing work in progress 3). 7LL OHSR—Third brace shuttering work in progress at Padalikkad Pack-2 Not Started | 19/12/2021 In this case, more discussion is required, After discussions, The meeting decided to reach an appropriate decision. As per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-3 Work in progress | 44% Completed | 19/12/2021 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – plinth beam concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- COLOUMN UP TO 3RD BRACE WORK completed and column work in progress 4) pumping main -400 mm DI K9 pipe- 6985.00 m supplied and 6400.00m laid 250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 21% Completed | 19/12/2021 Revised estimate as per latest DSR 2018 is under preparation for approval of PRICE escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.202 Pack-5 Work in progress | 87% Completed | 19/12/2021 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 70758.00M 2)110mm pvc,6kg/cm2 – 1134m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2232m 6)250mm DI K9 - 974m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-36M TOTAL – 80.977KM Chittur Project Dn - AE 2
12 Dec 2021 Pack-1 Work in progress | 34% Completed | 12/12/2021 Pack-1 1). 11 LL OHSR at JTS – 3RD BRACE BEAM shuttering and reinforcement work in progress at JTS Marutharoad 2). 8LL OHSR - Columns above 4th brace casting work completed and floor slab shuttering work progress at Malampuzha and pump house- column footing work in progress 3). 7LL OHSR-- Column and staircase concrete work above second brace work in progress at Padalikkad Pack-2 Not Started | 12/12/2021 In this case, more discussion is required, After discussions, The meeting decided to reach an appropriate decision. As per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-3 Work in progress | 44% Completed | 12/12/2021 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work in progress (2) 20LL OHSR – balance 20 numbers column footing work completed 3.) 11.50 LL OHSR -Cherad OHSR- COLOUMN UP TO 3RD BRACE WORK completed 4) pumping main -400 mm DI K9 pipe- 6985.00 m supplied and 5300.00m laid 250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 21% Completed | 05/12/2021 Revised estimate as per latest DSR 2018 is under preparation for approval of PRICE escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 86% Completed | 12/12/2021 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 - 68950.00M 2)110mm pvc,6kg/cm2 – 1134m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1525m 5)200mm DI K9 - 2110m 6)250mm DI K9 - 974m 7) 300mm DI K9 – 410m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 239m 10) 80 mm GI-36M TOTAL – 78.935KM Chittur Project Dn - AE 2
05 Dec 2021 Pack-1 Work in progress | 34% Completed | 05/12/2021 Pack-1 1). 11 LL OHSR at JTS - column above 3rd brace works in progress at JTS Marutharoad 2). 8LL OHSR - Columns above 4th brace casting work completed and floor slab shuttering work progress at Malampuzha and pump house- column footing work in progress 3). 7LL OHSR-- Column concrete work above second brace work in progress at Padalikkad Pack-2 Not Started | 05/12/2021 work not started pack-3 Work in progress | 44% Completed | 05/12/2021 1).8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work in progress (2) 20LL OHSR – balance 20 numbers column footing work completed 3.) 11.50 LL OHSR -Cherad OHSR- COLOUMN UP TO 3RD BRACE WORK completed 4) pumping main -400 mm DI K9 pipe- 6985.00 m supplied and 5300.00m laid 250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 21% Completed | 05/12/2021 Revised estimate as per latest DSR 2018 is under preparation for approval of PRICE escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 86% Completed | 05/12/2021 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M (PIPE LAID ) 1.)90mm pvc,6kg/cm2 - 68950.00M 2)110mm pvc,6kg/cm2 – 1134m 3) 140mm pvc,6kg/cm2 – 2944 m 4)160mm pvc,6kg/cm2 - 1525m 5)200mm DI K9 - 2110m 6)250mm DI K9 - 974m 7) 300mm DI K9 – 410m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 239m 10) 80 mm GI-36M TOTAL – 78.935KM Chittur Project Dn - AE 2