Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Sep 2022 PACK-1 Work in progress | 59% Completed | 29/09/2022 1) 11 LL OHSR at JTS – floor slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha – 3). 7LL OHSR— floor slab and beam concrete work completed at Padalikkad – plastering work progressing 4) Malampuzha pump house- roof slab shuttering and reinforcement work in progress, 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-tie beam concrete work in progress PACK-2 Not Started | 29/09/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work Pack-3 Work in progress | 85% Completed | 29/09/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- COLUMN ABOVE third brace concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 29/09/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 97% Completed | 29/09/2022 Road side concrete work in progress,valve chamber work completed linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
10 Sep 2022 Pack-1 Work in progress | 53% Completed | 10/09/2022 1) 11 LL OHSR at JTS – floor slab and beam concrete work completed at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 01 10/09/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work Pack-3 Work in progress | 84% Completed | 01 10/09/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above 2 end Brace 2 end lift column-concrete work progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara anchor block work in progress Pack-4 Work in progress | 22% Completed | 10/09/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 10/09/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
01 Sep 2022 Pack-1 Work in progress | 53% Completed | 01/09/2022 1) 11 LL OHSR at JTS – floor slab and beam concrete work completed at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 01/09/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work Pack-3 Work in progress | 84% Completed | 01/09/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above 2 end Brace 2 end lift column-concrete work progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara anchor block work in progress Pack-4 Work in progress | 22% Completed | 01/09/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 01/09/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
25 Aug 2022 Pack-1 Work in progress | 52% Completed |25/8/08/2022 1) 11 LL OHSR at JTS – floor slab reinforcement work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 25/08/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superenteding Engineer directed the contractor to start the work Pack-3 Work in progress | 80% Completed | 25/08/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above third brace -concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 25/08/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 25/08/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
24 Aug 2022 Pack-1 Work in progress | 52% Completed |24/8/08/2022 1) 11 LL OHSR at JTS – floor slab reinforcement work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 24/08/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superenteding Engineer directed the contractor to start the work Pack-3 Work in progress | 80% Completed | 24/08/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above third brace -concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 24/08/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 24/08/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
21 Aug 2022 Pack-1 Work in progress | 52% Completed |21/8/08/2022 1) 11 LL OHSR at JTS – floor slab reinforcement work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 21/08/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superenteding Engineer directed the contractor to start the work Pack-3 Work in progress | 80% Completed | 21/08/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above third brace -concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 21/08/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 21/08/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
15 Aug 2022 Pack-1 Work in progress | 52% Completed |15/8/08/2022 1) 11 LL OHSR at JTS – floor slab reinforcement work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 15/08/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superenteding Engineer directed the contractor to start the work Pack-3 Work in progress | 80% Completed | 15/08/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above second brace -concrete work progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 15/08/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 15/08/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
08 Aug 2022 Pack-1 Work in progress | 52% Completed | 08/08/2022 1) 11 LL OHSR at JTS – floor slab reinforcement work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha - 75% 3). 7LL OHSR— floor slab reinforcement work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab reinforcement work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 08/08/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superenteding Engineer directed the contractor to start the work Pack-3 Work in progress | 80% Completed | 08/08/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – column above second brace -concrete work progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 08/08/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 08/08/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
31 Jul 2022 Pack-1 Work in progress | 51% Completed | 31/07/2022 1) 11 LL OHSR at JTS – floor slab shuttering work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab shuttering work in progress at Malampuzha - 75% 3). 7LL OHSR— floor slab shuttering work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab shuttering work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started | 31/07/2022 As per the decision of meeting chaired by Hon. Minister for Water resources the estimate is recasted for KIIFB for approval. Pack-3 Work in progress | 78% Completed | 31/07/2022 1) 8LL OHSR-Mundur –plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – second brace concrete work in progress3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 31/07/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 96% Completed | 31/07/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
24 Jul 2022 Pack-1 Work in progress | 51% Completed | 24/07/2022 1) 11 LL OHSR at JTS – floor slab shuttering work in progress at JTS Marutharoad -50% 2). 8 LL OHSR – coverslab shuttering work in progress at Malampuzha - 75% 3). 7LL OHSR— floor slab shuttering work is in progress at Padalikkad - 48% 4) Malampuzha pump house- roof slab shuttering work in progress, - 40% 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid - 60% 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid - 62% 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-river crossing work-piers second lift work in progress - 50% 9) Pump sets - Not supplied Pack-2 Not Started |24/07/2022 As per the decision of meeting chaired by Hon. Minister for Water resources the estimate is recasting for submission to KIIFB for approval. Pack-3 Work in progress | 78% Completed | 24/07/2022 1) 8LL OHSR-Mundur –plastering work completed vertical column pipe erection completed. (2) 20LL OHSR – second brace form work and reinforcement work in progress3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 24/07/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract. Pack-5 Work in progress | 96% Completed | 24/07/2022 valve chamber work in progress, linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2