07 Sep 2023 Pack-1 Work in progress | 90% Completed | 07/09/2023 Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-2 Not Started | 07/09/2023 work tendered several times nobody participated pack-3 Work in progress | 93% Completed | 07/09/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 07/09/2023 WORK NOT STARTED pack-5 work foreclosed on 24.08.2022 Chittur Project Dn - AE 2
12 Aug 2023 Pack-1 Work in progress | 90% Completed | 12/08/2023 Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work Pack-2 Not Started | 12/08/2023 work tendered several times nobody participated pack-3 Work in progress | 93% Completed | 12/08/2023 Pumping main - work completed except Trail running , Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – work complete except painting, lightening arrestor, fixing ladder inside of tank (2) 20LL OHSR –puthupperiyaram -valayakkad- work completed except plastring ,compound wall,painting, lightening arrestor, fixing ladder inside of tank 3.) 11.50 LL OHSR at cherad - work completed except painting, lightening arrestor, fixing ladder inside of tank 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 12/08/2023 WORK NOT STARTED pack-5 work foreclosed on 24.08.2022 Chittur Project Dn - AE 2
03 Aug 2023 Pack-1 Work in progress | 90% Completed | 03/08/2023 Railway crossing work,valve chambers work, colour washing ,finishing works are also in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – floor levelling works and white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work completed and painting work balance Pack-2 Not Started | 03/08/2023 work re tendered -nobody participated pack-3 Work in progress | 93% Completed |03/08/2023 valve chamber work and scour pipe line laying work also progress Trail running and 400mm DI line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara pack-4 Not Started | 03/08/2023WORK NOT STARTED Chittur Project Dn - AE 2
20 Jul 2023 Pack-1 Work in progress | 90% Completed | 20/07/2023 Railway crossing work,valve chambers work, colour washing ,finishing works are also in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – floor levelling works and white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work completed and painting work balance Pack-2 Not Started | 20/07/2023 work re tendered -nobody participated pack-3 Work in progress | 93% Completed | 20/07/2023 valve chamber work and scour pipe line laying work also progress Trail running and 400mm DI line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara pack-4 Not Started | 20/07/2023 WORK NOT STARTED Chittur Project Dn - AE 2
13 Jul 2023 Pack-1 Work in progress | 90% Completed | 13/07/2023 Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – floor levelling works and white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work completed and painting work balance Pack-2 Not Started | 13/07/2023 work re tendered -nobody participated pack-3 Work in progress | 93% Completed | 13/07/2023 valve chamber work and scour pipe line laying work also progress Trail running and 400mm DI line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara pack-4 Not Started | 13/07/2023 WORK NOT STARTED Pack-5 THE WORK IS FORE CLOSED Chittur Project Dn - AE 2
06 Jul 2023 PACK-1 Work in progress | 90% Completed | 06/07/2023 Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work completed and painting work balance PACK-2 Not Started | 06/07/2023 work retendered -nobody participated PACK-3 Work in progress | 93% Completed | 06/07/2023 Trail running and 400mm DI line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-4 Not Started | 06/07/2023 WORK NOT STARTED Chittur Project Dn - AE 2
29 Jun 2023 Pack-1 Work in progress | 90% Completed | 29/06/2023 Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work completed and painting work balance Pack-2 Not Started | 29/06/2023 work retendered -nobody participated PACK-3 Work in progress | 93% Completed | 29/06/2023 Trail running and 400mm DI line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-4 Not Started | 29/06/2023 WORK NOT STARTED Chittur Project Dn - AE 2
23 Jun 2023 Pack-1 Work in progress | 90% Completed | 23/06/2023 Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress Pack-2 Not Started | 23/06/2023 tendering procedure processing PACK-3 Work in progress | 93% Completed | 23/06/2023 trail running and 400mm DI line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-4 Not Started | 23/06/2023 re tender procedure processing PACK-5 FORECLOSED Chittur Project Dn - AE 2
16 Jun 2023 Pack-1 Work in progress | 90% Completed | 16/06/2023 Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress Pack-2 Not Started | 16/06/2023 work re-tendered pack-3 Work in progress | 93% Completed | 16/06/2023 trail running and 400mm di line scouring at 1st air valve,Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed plastring work started 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara pack-4 Not Started | 16/06/2023 re tender procedure processing pack-5 97% of work c0mpleted work fore closed Chittur Project Dn - AE 2
09 Jun 2023 PACK-1 Work in progress | 90% Completed | 09/06/2023 Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress PACK-2 Not Started | 09/06/2023 work retendered PACK-3 Work in progress | 93% Completed | 09/06/2023 Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-4 Not Started | 09/06/2023 retender procedure processing Chittur Project Dn - AE 2