Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Mar 2022 Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam casting work in progress at JTS Marutharoad2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR— Columns first lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 4)350 mm DI K9 pipe - 4747 M pipe supplied and 800 m laid 5) 300mm DI pipe pumping main laying work in progress at Padalikkad-900m laid Pack-2 Not Started | 14/03/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 68% Completed | 14/03/2022 1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall third lift shuttering work in progress 4) .Pumping main -400 mm DI K9 pipe- 13255supplied and -9000.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 1946.80 m laid 7).250mm DI K9pipe-1254.00m supplied and 1130.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 14/03/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 93% Completed | 14/03/2022 supplied qty 80MM GI pipe-378 m ,125 mm GI -42m , 150mm GI-36M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72994.00M 2)110mm pvc,6kg/cm2 – 2080 m 3) 140mm pvc,6kg/cm2 – 3178 m 4)160mm pvc,6kg/cm2 - 1590 m 5)200mm DI K9 - 2368m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 93.402km Chittur Project Dn - AE 2
09 Mar 2022 Pack-1 Work in progress | 38% Completed | 09/03/2022 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam casting work in progress at JTS Marutharoad2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR— Columns shuttering and reinforcement work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 4)350 mm DI K9 pipe - 4747 M pipe supplied and 800 m laid 5) 300mm DI pipe pumping main laying work in progress at Padalikkad-600m laid Pack-2 Not Started | 09/03/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 68% Completed | 09/03/2022 1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall third lift shuttering work in progress 4) .Pumping main -400 mm DI K9 pipe- 13255supplied and -9000.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 1946.80 m laid 7).250mm DI K9pipe-1254.00m supplied and 1130.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 09/03/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 93% Completed | 09/03/2022 supplied qty 80MM GI pipe-378 m ,125 mm GI -42m , 150mm GI-36M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72994.00M 2)110mm pvc,6kg/cm2 – 2080 m 3) 140mm pvc,6kg/cm2 – 3178 m 4)160mm pvc,6kg/cm2 - 1590 m 5)200mm DI K9 - 2368m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 93.402km Chittur Project Dn - AE 2
02 Mar 2022 Pack-1- Work in progress | 37% Completed | 02/03/2022 1) 11 LL OHSR at JTS – Columns concrete casting above 4th brace work is in progress 2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR— Columns shuttering and reinforcement work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 4)350 mm DI K9 pipe - 4747 M pipe supplied and 800 m laid 5) 300mm DI pipe pumping main laying work in progress at Padalikkad-600m laid Pack-2 Not Started | 02/03/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 66% Completed | 02/03/2022 1) 8LL OHSR-Mundur –plastering work completed and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall second lift concrete work in progress 4) .Pumping main -400 mm DI K9 pipe- 13255. M-7939.80m , 350mm DI K9-308.90m supplied 400mm-8000.00m laid 250mm DI K9 -2975.50M SUPPLIED 1946.80 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid to akathethara Pack-4 Work in progress | 22% Completed | 02/03/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 PACK-5 Work in progress | 92% Completed | 02/03/2022 supplied qty 80MM GI pipe-378 m ,125 mm GI -42m , 150mm GI-36M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72940.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3178 m 4)160mm pvc,6kg/cm2 - 1553m 5)200mm DI K9 - 2310 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-157m 11)140mm GI-30m TOTAL – 83.972km Chittur Project Dn - AE 2
22 Feb 2022 PACK-1-work restarted vide supplementary agreement order No.KWA/PHC/PKD/KIIFB/Malampuzha/phase1/package-1/17-18 /dated 9.02.2022 Chittur Project Dn - AE 2
22 Feb 2022 Pack-1-WORK RESTARTED 11LL OHSR -4th brace beam casting work in progress at JTS Marutharoad 300 mm DI Pipe pumping main laying work in progress at Padalikkad towards JTS Marutharoad PACK-2 Not Started | 22/02/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date PACK-3 Work in progress | 65% Completed | 22/02/2022 1) 8LL OHSR-Mundur –plastering work completed and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall first inside column concrete work in progress 4) .Pumping main -400 mm DI K9 pipe- 13255. M-7939.80m , 350mm DI K9-308.90m supplied 400mm-8000.00m laid 250mm DI K9 -2975.50M SUPPLIED 1946.80 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid to akathethara PACK-4 Not Started | 22/02/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 PACK-5 Work in progress | 92% Completed | 22/02/2022 supplied qty 80MM GI pipe-378 m ,125 mm GI -42m , 150mm GI-36M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72940.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3178 m 4)160mm pvc,6kg/cm2 - 1553m 5)200mm DI K9 - 2310 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-157m 11)140mm GI-30m TOTAL – 83.972km Chittur Project Dn - AE 2
13 Feb 2022 Pack-1 Work in progress | 37% Completed | 13/02/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 13/02/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 63% Completed | 13/02/2022 1) 8LL OHSR-Mundur –plastering work completed and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall first inside column concrete work in progress 4) .Pumping main -400 mm DI K9 pipe- 13254. m ,350mm DI K9-280M supplied 400mm-8000.00m laid 250mm DI K9 -1540M SUPPLIED 800 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid to akathethara Pack-4 Work in progress | 22% Completed | 13/02/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 90% Completed | 13/02/2022 supplied qty 80MM GI pipe-180 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72890.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3166 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-126m TOTAL – 83.78km Chittur Project Dn - AE 2
06 Feb 2022 Pack-1 Work in progress | 37% Completed | 06/02/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 06/02/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 63% Completed | 06/02/2022 1) 8LL OHSR-Mundur –plastering work completed and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall first lift concrete work complete 4) .Pumping main -400 mm DI K9 pipe- 13254. m ,350mm DI K9-280M supplied 400mm-8000.00m laid 250mm DI K9 -1540M SUPPLIED 800 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid to akathethara Pack-4 Work in progress | 22% Completed | 06/02/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 90% Completed | 06/02/2022 supplied qty 80MM GI pipe-180 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72890.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3166 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-126m TOTAL – 83.78km Chittur Project Dn - AE 2
02 Feb 2022 PACK-I-The work was Terminated on 29.12.2021( vide order of Superintending Engineer No.KWA/PHC/PKD/KIIFB/Malampuzha/phase-I/pack-1 dtd 29.12.2021) Chittur Project Dn - AE 2
01 Feb 2022 Pack-1 Work in progress | 37% Completed | 01/02/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 01/02/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-4 Work in progress | 22% Completed | 01/02/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-3 Work in progress | 63% Completed | 01/02/2022 1) 8LL OHSR-Mundur –plastering work completed and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall first lift concrete work in progress 4) .Pumping main -400 mm DI K9 pipe- 13254. m ,350mm DI K9-280M supplied 400mm-8000.00m laid 250mm DI K9 -1540M SUPPLIED 800 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid to akathethara Pack-5 Work in progress | 90% Completed | 01/02/2022 supplied qty 80MM GI pipe-180 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72890.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3166 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-126m TOTAL – 83.78km Chittur Project Dn - AE 2
31 Jan 2022 Pack-1 Work in progress | 37% Completed | 31/01/2022 Work Terminated due to slow progress vide proceedings no KWA/PHC/PKD/KIIFB-Malampuzha/phase I/Package I-17-18 dtd 29.12.2021 of The Superintending Engineer, KWA, PH circle,Palakkad. Pack-2 Not Started | 31/01/2022 It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date Pack-3 Work in progress | 47% Completed | 31/01/2022 1) 8LL OHSR-Mundur -tank inside plastering almost complete and outside plastering work and handrail in progress , (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall first lift concrete work in progress 4) .Pumping main -400 mm DI K9 pipe- 8833.00 m supplied and 6800.00m laid 250mm DI K9 -1540M SUPPLIED 400 m laid , 5).250mm DI K9pipe-1254.00m supplied and 1230.80m laid Pack-4 Work in progress | 22% Completed | 31/01/2022 Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 Pack-5 Work in progress | 89% Completed | 31/01/2022 supplied qty 80MM GI pipe-90 m ,125 mm GI -30m , 150mm GI-24M ,(PIPE LAID ) 1.)90mm pvc,6kg/cm2 – 72831.00M 2)110mm pvc,6kg/cm2 – 1374m 3) 140mm pvc,6kg/cm2 – 3154 m 4)160mm pvc,6kg/cm2 - 1535m 5)200mm DI K9 - 2295 m 6)250mm DI K9 - 994m 7) 300mm DI K9 – 435m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-54M TOTAL – 83.601KM Chittur Project Dn - AE 2